Question

Green Bay Construction Company (“Green Bay”) was employed as a general contractor to build a football...

Green Bay Construction Company (“Green Bay”) was employed as a general contractor to build a football stadium entry. Green Bay employed Madison Swiss (“Swiss”), subcontractor, to complete the framing, trusses and other carpentry work on the stadium entryway in exchange for payment in the amount of $200,000. The written contract, stated that Swiss was to provide all labor, materials, tools, equipment, scaffolding, and workmanship, that the work was to be completed no later than June 15, 2013, and that when the work was completed Green Bay was to issue full payment.

On June 2, 2013, Swiss’s employees erected 38 trusses at the job site. On June 5, 2013, thirty (32) of the trusses broke, slipped and/or fell off, resulting in structural integrity concerns and problems. The reason for the trusses having fallen was unexplained, and Swiss was hesitant to continue work and fix the trusses arguing that they were deliberately knocked off. Green Bay told Swiss that they would pay Swiss an additional $50,000 to properly install the trusses and continue work. When the job was complete, Green Bay paid Swiss the original contract ($200,000) price but refused to pay Swiss the additional amount of $50,000. Swiss sued Green Bay for $50,000. Can Swiss recover? IRAC your answer.

I:          Under contract law does Green Bay owe Swiss $50,000 when Green Bay, general contractor, agreed to pay Swiss, subcontractor, an additional $50,000 to correct work already performed and to complete the work included in the original contract?

RULE:         

ANALYSIS:             

CONCLUSION:

Homework Answers

Answer #1

Rule- In contract law if two parties have contracted to do something for consideration and successfully completed the contract then the party have to pay the price.

Analysis- In this contract even though it was contracted for $200,000 initially and later Green Bay agreed to pay $50,000 extra for fixation of the trusses. Swiss have successfully completed the fixation work too. In no way Green Bay can withhold the payment.

Conclusion- Green bay has to pay swiss $50,000 in any case.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
BUSINESS LAW The Smith Construction Company, a general contractor, agrees to build a multi-story office building...
BUSINESS LAW The Smith Construction Company, a general contractor, agrees to build a multi-story office building for the Ace Computer Corporation at a total cost of $7,000,000.. After the project is completed, a representative from Ace Computer inspects the structure. The inspection reveals a significant problem with the electrical system. As a result, Ace Computer refuses to pay the $7,000,000 and take possession of the building. The representative from Smith Construction points out that the electrical work was completed by...
Hector is a building contractor and entered into a contract on February 1, 2018 to build...
Hector is a building contractor and entered into a contract on February 1, 2018 to build a house for Lois for $350,000 with a completion date of July 1, 2018. Payments are to be made to Hector by Lois of $50,000 on the signing of the contract, $150,000 on April 1, provided the house is partially completed as defined in the contract, and $150,000 on July 1, 2018, when the house is fully completed. Lois is very clear that the...
Mattel Responds to Ethical Challenges Business Ethics This case was written by Debbie Thorne, John Fraedrich,...
Mattel Responds to Ethical Challenges Business Ethics This case was written by Debbie Thorne, John Fraedrich, O. C. Ferrell, and Jennifer Jackson, with the editorial assistance of Jennifer Sawayda. This case was developed for classroom discussion rather than to illustrate either effective or ineffective handling of an administrative, ethical, or legal discussion by management. All sources used for this case were obtained through publicly available material. Mattel, Inc. is a world leader in the design, manufacture, and marketing of family...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how the firms resources incompetencies support the given pressures regarding costs and local responsiveness. Describe entry modes have they usually used, and whether they are appropriate for the given strategy. Any key issues in their global strategy? casestudy: Atlanta, June 17, 2014. Sea of Delta employees and their families swarmed between food trucks, amusement park booths, and entertainment venues that were scattered throughout what would...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT