Question

Give an example of a large project that took longer than a year to complete, Describe...

Give an example of a large project that took longer than a year to complete, Describe some of the tasks preformed to monitor and control the project,

Homework Answers

Answer #1

A large project that took longer than an year to complete was the construction of Hoover Dam which took a lot of year to complete and was constructed by a consortium of contractors, companies etc. Some of the tasks performed to monitor and control the project were:

1. Proper scheduling: Proper project scheduling was done and time was assigned to each and every activity so that the project is controlled in a better manner and is executed timely as well.

2. Workforce supervision: In order to monitor the activities in the project, proper supervision of the workforce was done and their performance was analyzed. Moreover the quality of work executed by them was verified so that the project is executed with precision.

3. Training: Proper training was provided to the workforce to perform critical jobs and hence it was automatically ensured that project was controlled in a better manner.

4. Scope of work: Scope of work was also properly designed and documented in order to clearly know the rules and responsibilities of each and every party and monitor the project in a proper manner.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Define project. Define the term project objective, and give some examples. List some examples of resources...
Define project. Define the term project objective, and give some examples. List some examples of resources that are used on a project. What role does a customer have during the project life cycle? Why is it important to satisfy the customer? What aspects of a project might involve some degree of uncertainty? Why? Define scope, schedule, cost, and customer satisfaction. Why are these considered to be constraints? List and describe the main phases of the project life cycle. List and...
How many tails are needed to find out if patients who took ascorbate lived longer than...
How many tails are needed to find out if patients who took ascorbate lived longer than 548 days? Select one: a. One tail, because the researcher only wants to know if life expectancy increased after ascorbate treatment. b. Either one-tail or two-tail, because both situations will tell if life expectancy changed. c. Two-tail, because the purpose of the study was to find if life expectancy changed. d. Either one-tail or two-tail, because both situations give the same answer.
what is meant by a flashbulb memory? Describe its characteristics. Give an example that is well-known....
what is meant by a flashbulb memory? Describe its characteristics. Give an example that is well-known. Some psychologists are not impressed by these well-known examples of this phenomenon. What are some of the criticisms of the idea of flashbulb memory?
Explain Piaget's theory of cognitive development. Give your own example of each stage. This should be...
Explain Piaget's theory of cognitive development. Give your own example of each stage. This should be a very complete answer Explain Eriksons' theory of life span development. How is it different from Freud's theory? You don't need to describe each stage, just summarize them please. Describe the three stages of pre-natal development and list one significant event that occurs in each stage. Which stage is known as the critical period and why? According to Kubler-Ross, what stages do terminally ill...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
First, give an example of a product or service that you purchased in the last year...
First, give an example of a product or service that you purchased in the last year for which your demand is relatively inelastic. You should explain what factors influenced why your demand for the selected product or service was inelastic. Be as specific as possible in your explanation. You may wish to review the factors influencing the elasticity of demand for a product to assist you in your explanations. Second, give an example of a product or service that you...
consider whether one process would result in more accuracy than another and discuss why.in the example...
consider whether one process would result in more accuracy than another and discuss why.in the example below. In order to have accurate top-down estimation, historical information must be used, which points to analogous estimating. Using a previous projects actual costs, an estimation using top-down may be done quickly and accurately if the projects are similar. However, estimates will not be accurate if two projects are not similar or only appeared to be similar, but this is an easy way to...
A client of Mr. Richards wants to purchase a large commercial building. The building costs $20...
A client of Mr. Richards wants to purchase a large commercial building. The building costs $20 million and he will make a down payment of 15% and finance the rest with a local bank. The bank terms are 10-year bullet loan with 30-year amortization at 4.5% interest. The building earns annual rent of $2,500,000 and it pays annual taxes of $1,000,000 per year. What will be the annual cash flow from the building? What will be the ROI on the...
1.) A large hospital in the Midwest, with more than 30,000 patients in a year, is...
1.) A large hospital in the Midwest, with more than 30,000 patients in a year, is interested in how long a patient had to wait from when they made the appointment to when they were seen. The hospital director is interested in learning this information so they can identify what section has the longest wait time and devote more resources to fix the problem. As such, the hospital director is going to sample from patients it has had in the...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT