Question

(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...

(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each.

3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of the text as well as in your statistics class on probability distributions. A table of Normal distribution will be provided to you.

TIME ESTIMATES (days)

ACTIVITY

PREDECSOR

OPTIMISTIC

MOST LIKELY

PESSIMISTIC

A

--

36

50

56

B

--

45

60

84

C

A

36

45

46

D

A,B

26

40

42

E

C

24

36

36

F

D,E

58

70

82

        

Complete the following information

Activity

Expected Duration

Variance of Duration

A

B

C

D

E

F

Draw (electronically) the AON network for this project. Using the expected durations as the activity duration, conduct CPM analysis of the network.

What is the estimated (i) expected (mean) time and (ii) Standard Deviation for project completion? What is the probability distribution of the project completion time? Why?

What is the probability that the critical path for this project will be completed within 210 days? 200 days?

If the client is comfortable with a 98.50 % of completing the project, what completion time would you recommend? [Please show your work].

Homework Answers

Answer #1

a)  

Characteristics Pure project teams Matrix Project Team
Reporting Team members report to only project manger Team memebers report to both Functional and Project Manager
Skills Pure project teams does not develop very specific skill of particular field or department In strong matrix structure, team has strong functional knowledge and return to same function post completion of project.

b)

PERT (BETA) Estimates = (optimistic duration + 4* Most Likely + pessimistic duration)/6

Variance = [( Pessimistic - optimistic duration)/6]2

ACTIVITY PREDECSOR OPTIMISTIC MOST LIKELY PESSIMISTIC Beta (PERT) Estimate Variance
A -- 36 50 56 48.67 11.11
B -- 45 60 84 61.50 42.25
C A 36 45 46 43.67 2.78
D A,B 26 40 42 38.00 7.11
E C 24 36 36 34.00 4.00
F D,E 58 70 82 70.00 16.00

Table :

ACTIVITY Beta (PERT) Estimate Variance
A 48.67 11.11
B 61.50 42.25
C 43.67 2.78
D 38.00 7.11
E 34.00 4.00
F 70.00 16.00

AON Network Diagram

Three paths are in network diagram

calculated sum of duration of each activities in path

Path Duration
Start- A-C-E-F-Finish 196.33
Start-A-D-F-Finish 156.67
Start- B-D-F-Finish 169.50

Longest path = Critical path = Duration of project

Critical Path = Start- A-C-E-F-Finish

i) Expected (Mean) time = critical path duration = 196.33

ii) Standard Deviation of project = sqrt ( Sum of Variance of Critical path activities) = sqrt(33.89) = 5.8

iii) Probability distribution is Normal districution with mean 196.3 & std dev 5.8 and range = (Mean-3*Std.dev, Mean+std.dev) =(196.33-3*5.8 , 196.33+3*5.8) = (178.8 , 213.8)

Z = (X-Mean)/Std. dev

at X= 210

z = (210- 196.33)/5.8 = 2.34

Refer Z table to find the Proablility

P(X<210) = Value probability of Z at 2.34 = 0.9904 = 99.04%

At X =200

Z = (200 - 196.33)/5.8 = 0.63

P(X<200) = 0.7357 = 73.57 %

At probability of 98.50 % i.e 0.9850 , z value from table = 2.17

Z = (X-Mean)/Std. dev

2.17 = (x-196.33)/5.8

X = 196.33 +2.17*5.8 = 208.9 = 209 days

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Based on the 10 Operation Decisions Table, we would begin with the product and end with...
Based on the 10 Operation Decisions Table, we would begin with the product and end with layout and location. True False Gantt charts are low-cost means of helping managers make sure that 1. activities are planned, 2. order of performance is documented, 3. activity time estimates are recorded, and 4. overall project time is developed. Gantt charts, thought, do not illustrate the interrelationships between the activities and the resources. True False Optimistic time, Pessimistic time and Most likely time are...
If a project has an expected time of completion Te of 45 weeks with a standard...
If a project has an expected time of completion Te of 45 weeks with a standard deviation of 7 weeks, what is the probability of completing it (a) within one year (52 weeks)? (b) within 38 weeks. Please solve the problem using PERT , Optimistic time, most likely time, and pessimistic time. Using this formula : Te = (To + 4Tm + Tp) / 6
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
A project has the following tasks and duration estimates given. These three tasks are done in...
A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation...
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT