Question

the success of a project is measured by the extent to which the project objectives have...

the success of a project is measured by the extent to which the project objectives have been met. for the project to ensure that there is earned value (EV). the earned value method (EVM) is used. it's of greatest importance that the cost estimate and the schedule are correct and that they align.
2.1 there are a few parameters that form the babes of the EV notion. list the items and provide the acronyms for each.

Homework Answers

Answer #1

The items that form the basis of the EV notion and their acronyms are:

  • Planned Value (PV) or the Budgeted cost for work scheduled (BCWS)- describes how much of the work should be completed at a given point of time
  • Earned Value (EV) or the Budgeted cost for work performed (BCWP)- quantifies the work done till date
  • Budget at completion (BAC)- the sum of the budgets allocated to the scope of the project
  • Actual cost of work performed (ACWP)- tells the costs incurred while executing the project
  • Estimate at completion (EAC) -is the cumulative actual cost of work performed till date plus the estimate to complete the remaining work.
  • Cost variance (CV) is the difference between the earned value and actual cost. A result greater than 0 is favourable, a result of less than 0 is unfavourable.
  • Schedule variance (SV) is the difference between the earned value and planned value A result greater than 0 is favourable (, a result less than 0 is unfavourable.
  • Variance at completion (VAC) is the difference between BAC and EAC. A result greater than 0 is favourable, a result of less than 0 is unfavourable.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer...
Como Tool and Die was a second-tier component supplier to the auto industry. Its largest customer was Ford Motor Company. Como had a reputation for delivering a quality product. During the 1980s and the early 1990s, Como’s business grew because of its commitment to quality. Emphasis was on manufacturing operations, and few attempts were made to use project management. All work was controlled by line managers who, more often than not, were overburdened with work. The culture at Como underwent...
Please show me how to apply CVP analysis for this case study. FLY ASH BRICK PROJECT:...
Please show me how to apply CVP analysis for this case study. FLY ASH BRICK PROJECT: FEASIBILITY STUDY USING CVP ANALYSIS S. K. Mitra and Shubhra Hajela wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be transmitted, photocopied, digitized or otherwise reproduced in any...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Please read the article and answear about questions. Determining the Value of the Business After you...
Please read the article and answear about questions. Determining the Value of the Business After you have completed a thorough and exacting investigation, you need to analyze all the infor- mation you have gathered. This is the time to consult with your business, financial, and legal advis- ers to arrive at an estimate of the value of the business. Outside advisers are impartial and are more likely to see the bad things about the business than are you. You should...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation. case:    W17400 APIGEE: PEOPLE MANAGEMENT PRACTICES AND THE CHALLENGE OF GROWTH Ranjeet Nambudiri, S. Ramnarayan, and Catherine Xavier wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be...