Question

1.       Select the group of words missing from the statement below about the Modified Internal Rate...

1.       Select the group of words missing from the statement below about the Modified Internal Rate of Return (MIRR).

“The MIRR allows for any ________ cash flows produced by an investment over the project period to be _________ at a chosen ________ rate rather than the _____ of the project. It also allows any _______ cash flows to be discounted back to the present time at the ________ rate to determine how much needs to be set aside today in order to fund future cash outflows.”

a)      Project, Discounted, Discount, NPV, Positive, Interest

b)      Positive, Discounted, Reinvestment, NPV, Negative, Interest

c)       Project, Reinvested, Discount, IRR, Positive, Finance

d)      Positive, Reinvested, Reinvestment, IRR, Negative, Finance

2.   Which of the following can be said to be some of the disadvantages of Capital Rationing?

a)      By using capital rationing techniques and investing only in selected projects, Capital Rationing effectively ignores the theory that managers should invest in all projects that add value to the company and increase shareholder wealth.

b)      Capital rationing allows all unprofitable projects to be accepted and so profits are not maximized.

c)       Capital rationing places restrictions on the cost of capital applied to project cash flows and the hurdle rates used to measure profitability.

d)      Capital rationing excludes from evaluation and the selection criteria, any intermediate cash flows from a project.

Homework Answers

Answer #1

1. d) Positive, Reinvested, Reinvestment, IRR, Negative, Finance

MIRR assumes that positive cash flows from the investment on a new project are reinvested at the firm's cost of capital and not at IRR and the initial investments are financed at the firm's financial cost.

2. a), c), d)

By following capital rational, a firm invests only in certain projects and not in all the profitable projects violating efficient capital markets theory.

Selective criteria is applied while calculating cost of capital of shortlisted projects. The firm should accurately calculate cost of capital to avoid selecting less profitable poject.

Capital rational only considers the final returns from a project and excludes intermediate cashflows while evaluating a project

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment of $500,000....
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation : Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $3,225,000....
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
1.       Select the group of words missing from the statement below about the nature of cash...
1.       Select the group of words missing from the statement below about the nature of cash budgets: “Cash budgets are prepared to reflect the estimated cash ______ and _______ for the period to be covered by the budget. Clearly a projected _______ cash balance will require corrective action. Even if the cash budget predicts a _______ net balance, it may be necessary to review it to take into account any potential ________ in the expected cash flows or to provide...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT