Question

When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...

When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR.

It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method.

Let's try to find the MIRR for the project with the following cash flows:

Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130.

Here we have two negative cash flows and two positive cash flows.

Step 1: find PV of two costs at the discount rate = WACC of 7%;

Step 2 : find FV of two inflows at 7%;

Step 3: find the discount rate that makes PV from step 1 equal to FV from step 2. That is MIRR.

Make a decision on accepting or rejecting the project by comparing MIRR to the WACC.

Homework Answers

Answer #1

When there is sign change of chasflows for more than once, there will be more than one IRR which is misleading and contradicting with NPV method. Hence, MIRR Ussed.

Year 0 1 2 3
Cashflow -800 400 570 -130
WACC 7%
PV of all (-) CF at 0 -906.119
-800 - 130 /(1+0.07)^3
FV of all(+) CF at t=3 1067.86
400*(1.07)^2+570*(1.07)
Lets assume MIRR 5.63%
906.119 X(1+MIRR)^3 = 1067.86

Since, MIRR is < WACC, hence, it si not generating cash enough rate by which we have borrowed cash from outside. Hence, Project should be rejected.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. Is this a good project if the required return is 8 percent? What if it's 24 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?  LO 4 9. Calculating NPV. For the cash flows in the previous problem, what is the NPV at a discount rate of...
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years...
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years costs $7,560 today. 1. The NPV is $__________if the required rate of return is 10%. 2. The NPV is $__________if the required rate of return is 24%. 3. At what discount rate would you be indifferent between accepting the project and rejecting it? I would be indifferent at _____% 4. Using a finnancial calculator please show and explain work.
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has NO tax. ABC Ltd. is considering investing in a 2-year project which is expected to generate the following year-end cash flows: C1 = $110 million, C2 = $115 million. The yearly discount rate for the project is 10%. The initial cost of the project is $200 million. (a) Compute the profit and NPV of the project. (b) Based on the answer of part (a),...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has NO tax. ABC Ltd. is considering investing in a 2-year project which is expected to generate the following year-end cash flows: C1 = $110 million, C2 = $115 million. The yearly discount rate for the project is 10%. The initial cost of the project is $200 million. (a) Compute the profit and NPV of the project. (b) Based on the answer of part (a),...