Question:A CSP plant with 4 hours of thermal storage needs to be
designed. The capacity of...
Question
A CSP plant with 4 hours of thermal storage needs to be
designed. The capacity of...
A CSP plant with 4 hours of thermal storage needs to be
designed. The capacity of the plant is 50 MWe. The efficiency of
“solar to electric” is 0.08.
a) What is the thermal energy required for this plant without
storage?
b) Assuming the power plant operates for 8 hours during the
day on solar, 4 hours on thermal storage and remaining hours with
fossil fuel backup, find the total energy needed to be supplied by
solar. Assume 100% TES.
c) If the solar multiple is 2.2, what is the solar field
design point thermal output?