Question

A project's base case or most likely NPV is $44,000, and assume its probability of occurrence...

A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 85% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best case scenario and the worst case scenario have a 25% probability of occurrence. Find the project's coefficient of variation.

Homework Answers

Answer #1

Base Case:

Probability of Occurrence = 50%
NPV = $44,000

Best Case:

Probability of Occurrence = 25%

NPV = $44,000 + 85% * $44,000
NPV = $81,400

Worst Case:

Probability of Occurrence = 25%

NPV = $44,000 - 35% * $44,000
NPV = $28,600

Expected NPV = 0.50 * $44,000 + 0.25 * $81,400 + 0.25 * $28,600
Expected NPV = $49,500

Variance = 0.50 * (44,000 - 49,500)^2 + 0.25 * (81,400 - 49,500)^2 + 0.25 * (28,600 - 49,500)^2
Variance = 378,730,000

Standard Deviation = (378,730,000)^(1/2)
Standard Deviation = $19,460.99

Coefficient of Variation = Standard Deviation / Expected NPV
Coefficient of Variation = $19,460.99 / $49,500
Coefficient of Variation = 0.393

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 50% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is...
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 70% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70 Variable cost: $ 50 Fixed cost: $ 200,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$76 million     Below average 0.20 -28 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$72 million     Below average 0.20 -18 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$74 million     Below average 0.20 -12 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome         NPV Recession 0.05 -$68 million     Below average 0.20 -18 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$76 million     Below average 0.20 -12 million    ...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT