Question

A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...

A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 70% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

Homework Answers

Answer #1

Best Case NPV = 50000*(1+70%) =85000
Worst Case NPV =50000*(1-30%) =35000
Expected NPV = Probability of base Case* NPV of base case + Probability of best Case scenario *NPV of best case scenario + Probability of Worst Case scenario *NPV of worst case scenario =60%*50000+20%*50000*(1+70%)+20%*50000(1-30%)
=54000

Standard Deviation =(60%*(50000-54000)^2+20%*(85000-54000)^2+20%*(35000-54000)^2)^0.5 =16552.95

Coefficient of Variation =Standard Deviation/Expected Return =16552.95/54000 =0.31

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence...
A project's base case or most likely NPV is $50,000, and assume its probability of occurrence is 60%. Assume the best case scenario NPV is 50% higher than the base case and assume the worst scenario NPV is 30% lower than the base case. Both the best case scenario and the worst case scenario have a 20% probability of occurrence. Find the project's coefficient of variation. Enter your answer rounded to two decimal places. For example, if your answer is...
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence...
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 85% higher than the base case and assume the worst scenario NPV is 35% lower than the base case. Both the best case scenario and the worst case scenario have a 25% probability of occurrence. Find the project's coefficient of variation.
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70 Variable cost: $ 50 Fixed cost: $ 200,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 280,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$76 million     Below average 0.20 -28 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$72 million     Below average 0.20 -18 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$74 million     Below average 0.20 -12 million    ...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's...
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome         NPV Recession 0.05 -$68 million     Below average 0.20 -18 million    ...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT