Question

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...

The most likely outcomes for a particular project are estimated as follows:

Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year

However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 40% and the required rate of return is 12%.

a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

b. What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

Homework Answers

Answer #1

Best-case scenario: N = 47,000 x (1 + 10%) = 51,700, P = 60 x 1.1 = 66, VC = 40 x (1 - 10%) = 36, FC = 378,000

Annual Cash Flow = (51,700 x (66 - 36) - 378,000 - 210,000) x (1 - 40%) + 210,000 = $787,800

N = 10, I/Y = 12%, PMT = 787,000, FV = 0 => Compute PV = $4,451,246

NPV (best- case scenario) = 4,451,246 - 2,100,000 = $2,351,246

Worst-case scenario: N = 47,000 x (1 - 10%) = 42,300, P = 60 x 0.9 = 54, VC = 44, FC = 462,000

Annual Cash Flow = $60,600

N = 10, I/Y = 12%, PMT = 60,600, FV = 0 => Compute PV = $342,404

NPV (worst case scenario) = 342,404 - 2,100,000 = -$1,757,596

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 280,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70 Variable cost: $ 50 Fixed cost: $ 200,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
Unit Price: $60, Variable Cost: $40, Fixed-Cost $420,000, Expected Sales: 47,000 Units per year However, you...
Unit Price: $60, Variable Cost: $40, Fixed-Cost $420,000, Expected Sales: 47,000 Units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is...
the mostly outcomes for a particular project are estimated as follows: Unit Price: $50 Variable Cost:...
the mostly outcomes for a particular project are estimated as follows: Unit Price: $50 Variable Cost: $30 Fixed Cost: $490000 Expected sales: 48000 units per year however, you recognize that some of the estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. the project will last for 10 years and require an initial investment of $2.3 million, which will be depreciated straight line over the...
Consider a project to produce solar water heaters. It requires a $10 million investment and offers...
Consider a project to produce solar water heaters. It requires a $10 million investment and offers a level after-tax cash flow of $1.69 million per year for 10 years. The opportunity cost of capital is 11.25%, which reflects the project’s business risk. a. Suppose the project is financed with $7 million of debt and $3 million of equity. The interest rate is 7.25% and the marginal tax rate is 21%. An equal amount of the debt will be repaid in...
You are considering a new product launch. The project will cost $740,000, have a 4-year life,...
You are considering a new product launch. The project will cost $740,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 430 units per year; price per unit will be $17,600, variable cost per unit will be $14,300, and fixed costs will be $710,000 per year. The required return on the project is 11 percent, and the relevant tax rate is 22 percent.    a. The unit sales, variable cost, and...
Grand Banks Mining Inc. plans a project to strip-mine a wilderness area. Setting up operations and...
Grand Banks Mining Inc. plans a project to strip-mine a wilderness area. Setting up operations and initial digging will cost $5 million. The first year's operations are expected to be slow and to net a positive cash flow of only $500,000. Then there will be four years of $2 million cash flows after which the ore will run out. Closing the mine and restoring the environment in the sixth year will cost $1 million. Calculate the project's NPV at a...
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment...
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.27 million. The fixed asset qualifies for 100 percent bonus depreciation in the first year. The project is estimated to generate $1,800,000 in annual sales, with costs of $692,000. The project requires an initial investment in net working capital of $430,000, and the fixed asset will have a market value of $450,000 at the end of the project. a. If the tax rate...
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment...
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.27 million. The fixed asset qualifies for 100 percent bonus depreciation in the first year. The project is estimated to generate $1,800,000 in annual sales, with costs of $692,000. The project requires an initial investment in net working capital of $430,000, and the fixed asset will have a market value of $450,000 at the end of the project. a. If the tax rate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT