Question

Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...

Two projects being considered are mutually exclusive and have the following cash flows:

Year

Project A

Project B

0

−$50,000

−$50,000

1

15,625

0

2

15,625

0

3

15,625

0

4

15,625

0

5

1,562

89,500

If the required rate of return on these projects is 13 percent, which would be chosen and why?

a.

Project B because of higher NPV.

b.

Project B because of higher IRR.

c.

Project A because of higher NPV.

d.

Project A because of higher IRR.

e.

Neither, because the cost of capital is too high.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 −$50,000 −$50,000 1 15,625 0 2 15,625 0 3 15,625 0 4 15,625 0 5 1,562 89,500 If the required rate of return on these projects is 13 percent, which would be chosen and why? a. Project B because of higher NPV. b. Project B because of higher IRR. c. Project A because of higher NPV. d. Project A because of...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 99,000 If the required rate of return on these projects is 10 percent, which would be chosen and why?
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows:      Year                               Project A                       Project B                                             Cash Flow                     Cash flow        0                                      (2000)                            (2000)        1                                         0                                     832        2                                         0                                     832        3                                         0                                     832        4                                       3877                                 832                                  Based only on the information given, which of the projects would be preferred and why? Mark the correct answer but justify your answer showing your computations. a.Project A, because it has...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: A....