Question

Consider two projects, A and B. Project A's first cash flow is $10,500 and is received...

Consider two projects, A and B. Project A's first cash flow is $10,500 and is received three years from today. Future cash flows for Project A grow by 4 percent in perpetuity. Project B's first cash flow is −$9,200, which occurs two years from today, and will continue in perpetuity. Assume that the appropriate discount rate is 12 percent.

A) What is the present value of each project? (a negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places.

Present Value

Project A $?

Project B $?

B) Suppose that the two project are combined into one project, called C. What is the IRR of Project C? (Do not round intermediate calculations and round your answers to 2 decimal places.)

IRR= ?%

C) What is the correct IRR rule for Project C?

-Accept the project if the discount rate is above the IRR

-Accept the project if the discount rate is equal the IRR

-Accept the project if the discount rate is below the IRR

Homework Answers

Answer #1

Hello,

Here is the solution to your question -

a)

Project A

The first cash flow is at t=3 of $10500

Also from t = 4 onwards, cash flow grow by 4% till perpetuity. To calculate PV of this cash flow till perpetuity at t=2, use the following formula

PVt=2 = FV/i-g

where FV = 10500

i = discount rate = 12%

g = growth rate = 4%

so, PVt=2 = 10500/0.12-0.04 = $131250

So, Finally,

PV of Project A at t=0 = $131250 discounted at 12% over 2 years = 131250/(1.12)^2 = $104631.7

Project B

PVt=1 = FV/i = -9200/0.12 = -$76666.67

So, finally,

PV of Project B at t=0 = - $76666.67 discounted at 12% for 1 year = - $68452.38

b) If both the projects are combined, then

NPV = PV of Project A + PV of Project B = 104631.7 - 68452.38 = $ 36179.32

c) The correct IRR rule for Project C is this -

Accept the project if the discount rate is below the IRR

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 424,000 –$ 39,500 1 44,500 20,300 2 61,500 13,400 3 78,500 18,100 4 539,000 14,900    The required return on these investments is 11 percent. a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period Project A years Project B years b. What is the NPV for each...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000       –$180,000       1 25,000       15,000       2 22,000       45,000       3 20,000       50,000       4 15,000       275,000       The required return on these investments is 11 percent. Required: (a) What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Payback period   Project A years     Project B years  ...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash Flow (B) 0 –$ 28,000 –$ 28,000 1 13,400 3,800 2 11,300 9,300 3 8,700 14,200 4 4,600 15,800    a-1 What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Project A %   Project B %    a-2 Using the IRR decision rule, which...
Consider the following two mutually exclusive projects:     Year Cash Flow (X) Cash Flow (Y) 0...
Consider the following two mutually exclusive projects:     Year Cash Flow (X) Cash Flow (Y) 0 –$ 20,900 –$ 20,900 1 9,075 10,550 2 9,550 8,025 3 9,025 8,925      Calculate the IRR for each project. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)     IRR   Project X %     Project Y %     What is the crossover rate for these two projects? (Do not round intermediate calculations. Enter your answer...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$ 341,000 –$ 51,000    1 54,000 24,900    2 74,000 22,900    3 74,000 20,400    4 449,000 15,500    Whichever project you choose, if any, you require a return of 15 percent on your investment.    a-1 What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)    a-2...
Consider the following cash flows of two mutually exclusive projects for A–Z Motorcars. Assume the discount...
Consider the following cash flows of two mutually exclusive projects for A–Z Motorcars. Assume the discount rate for both projects is 12 percent. Year AZM Mini-SUV AZF Full-SUV 0 –$ 525,000 –$ 875,000 1 335,000 365,000 2 210,000 450,000 3 165,000 305,000 a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period AZM Mini-SUV years AZF Full-SUV years b. What is the NPV for...
Garage, Inc., has identified the following two projects: Year Cash flow (A) Cash flow(B) 0 -$29,000...
Garage, Inc., has identified the following two projects: Year Cash flow (A) Cash flow(B) 0 -$29,000 -$29,000 1 14,400 4,300 2 12,300 9,800 3 9,200 15,200 4 5,100 16,800 A and B are independent projects. Assume that the required rate of return is 11 percent. 1. What is Project B's NPV? 2. A and B are independent projects. Assume that the required rate of return is 11 percent. Which project(s) should be accepted according to the NPV criterion? 3. A...
A project has a forecasted cash flow of $128 in year 1 and $139 in year...
A project has a forecasted cash flow of $128 in year 1 and $139 in year 2. The interest rate is 7%, the estimated risk premium on the market is 12%, and the project has a beta of .68. If you use a constant risk-adjusted discount rate, what is: a. The PV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Present value            $ b. The certainty-equivalent cash flow in year 1 and year...
What is the present value of an annuity of $6,000 per year, with the first cash...
What is the present value of an annuity of $6,000 per year, with the first cash flow received three years from today and the last one received 25 years from today? Use a discount rate of 7 percent. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      Present value $   
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 11 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,740,000 –$ 770,000 1 1,104,000 395,000 2 908,000 640,000 3 754,000 398,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT