Question

The NPV decision rule says to accept the project if the NPV is greater than zero....

The NPV decision rule says to accept the project if the NPV is greater than zero. You perform a thorough capital budgeting analysis on a project that requires a $1,000,000,000 initial investment and calculate the net present value (NPV) as $1. Following the rule, you tell your boss she should accept the project. She laughs and says “do you think I would really invest $1,000,000,000 for a measly $1 NPV? You should be fired” How would you respond to her?

Homework Answers

Answer #1

Net Present Value (NPV) is calculated by discounting the future cash inflows at Minimum Acceptable Rate of Return (MARR) and then subtracting the initial investment.

$1 NPV does not mean that the profit is $1.

$1 is the wealth created for the shareholders after providing for the required return to the shareholders.

While deciding on the MARR , the cost of capital and the project risks are also taken into account.

Hence ,the investment opportunity of $1,000,000,000 will be an opportunity for the organization to grow after making the required profit and providing for all costs including costs of debt.

If the company can arrange for the required capital and if there is no other better opportunity, this project should be considered as opportunity to grow and should be taken up

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
A firm evaluates all of its projects by applying the NPV decision rule. A project under...
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows: Year Cash Flow 0 –$ 28,300 1 12,300 2 15,300 3 11,300 1.What is the NPV for the project if the required return is 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV    2.At a required return of 11 percent, should the firm accept this project? Yes No...
A firm evaluates all of its projects by applying the NPV decision rule. A project under...
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows: Year Cash Flow 0 –$ 27,400 1 11,400 2 14,400 3 10,400 What is the NPV for the project if the required return is 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ At a required return of 12 percent, should the firm accept this project? No Yes...
A firm evaluates all of its projects by applying the NPV decision rule. A project under...
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows:    Year Cash Flow 0 –$ 28,800 1 12,800 2 15,800 3 11,800    What is the NPV for the project if the required return is 10 percent? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))      NPV =$    At a required return of 10 percent, should the firm...
A firm evaluates all of its projects by applying the NPV decision rule. A project under...
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows:    Year Cash Flow 0 –$ 28,500 1 12,500 2 15,500 3 11,500    What is the NPV for the project if the required return is 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $       At a required return of 10 percent, should the firm accept...
A firm evaluates all of its projects by applying the NPV decision rule. A project under...
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows:    Year Cash Flow 0 –$ 27,500 1 11,500 2 14,500 3 10,500    What is the NPV for the project if the required return is 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ At a required return of 11 percent, should the firm accept this project?...
The NPV rule states that, “An investment should be accepted if the net present value (...
The NPV rule states that, “An investment should be accepted if the net present value ( NPV) is positive and rejected if it is negative.” What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV ( or very close to zero) what would you do? Why?
1. NPV According to the text, the NPV rule states that "An investment should be accepted...
1. NPV According to the text, the NPV rule states that "An investment should be accepted if the NPV is positive and rejected if it is negative." What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV (or very close to zero) what would you do? Why? 2. FORECASTING ERROR (RISK) What is a "forecasting error"? Why is it important to the analysis of capital expenditure projects? please, original work.
Senior management asks you to recommend a decision on which project(s) to accept based on the...
Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided. Relevant information: The firm uses a 3-year cutoff when using the payback method. The hurdle rate used to evaluate capital budgeting projects is 15%. The cash flows for projects A, B and C are provided below. Project A Project B Project C Year 0 -30,000 -20,000 -50,000 Year 1 0 4,000 20,000 Year 2 7,000 5,000 20,000 Year 3 20,000...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,750,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $325,000 Year 2 $475,000 Year...