Question

Senior management asks you to recommend a decision on which project(s) to accept based on the...

Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided.

Relevant information:

  1. The firm uses a 3-year cutoff when using the payback method.
  2. The hurdle rate used to evaluate capital budgeting projects is 15%.

The cash flows for projects A, B and C are provided below.

Project A

Project B

Project C

Year 0

-30,000

-20,000

-50,000

Year 1

0

4,000

20,000

Year 2

7,000

5,000

20,000

Year 3

20,000

6,000

20,000

Year 4

20,000

7,000

5,000

Year 5

10,000

8,000

5,000

Year 6

5,000

9,000

5,000

  1. Assume the projects are independent and answer the following:
    • Calculate the payback period for each project.
    • Which project(s) would you accept based on the payback criterion?
    • Calculate the internal rate of return (IRR) for each project.
    • Which projects would you accept based on the IRR criterion?
    • Calculate the net present value (NPV) for each project.
    • Which projects would you accept based on the NPV criterion?
  2. Assume the projects are mutually exclusive and answer the following:
    • Which project(s) would you accept based on the payback criterion?
    • Which projects would you accept based on the IRR criterion?
    • Which projects would you accept based on the NPV criterion?

Submission Instructions:

  • Complete and submit the assignment by 23:59 Sunday.
  • You should submit your completed work in a Word document or Excel spreadsheet if needed.

Grading Rubric

Homework Answers

Answer #1

The payback period is the number of years it takes for the project to break even, i.e the number of years it takes for the sum of the cashflow to be higher than the initial investment

For Project A, this occurs after the 3rd year ( -30,000 + 0 + 7,000 + 20,000 + 20,000 > 0 )

For Project B, this occurs after the 3rd year ( -20,000 + 4,000 + 5,000 + 6,000 + 7,000 > 0 )

For Project C, this occurs after the 2nd year ( -50,000 + 20,000 + 20,000 + 20,000 > 0 )

Based on payback period, Project C should be selected

Projects with IRR greater than the required rate of return (hurdle rate) should be accepted.

Projects with positive NPV should be selected.

Based on IRR, Project A should be selected.

Based on NPV, Project A should be selected.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II)...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II) 0 -$12,300 -$44,000 1 $1,800 $14,000 2 $6,000 $30,000 3 $2,000 $5,000 4 $5,000 $10,000 5 $7,000 $5,000 The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively. a) Which project will you choose if you apply the NPV criterion? Why? b) Which project will you choose...
(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV,...
(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV, IRR and PayBack Period (c) Develop Problem-Solving and Critical Thinking Skills 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $   200,000 2) New equipment cost $ (200,000) 9) Sales increase per year 5% 3) Equipment ship & install cost $     (35,000) 10) Operating cost: $ (120,000) 4) Related start up cost $       (5,000)     (60 Percent of...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR and PayBack Period 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $     200,000 2) New equipment cost $          (200,000) 9) Sales increase per year 4% 3) Equipment ship & install cost $            (25,000) 10) Operating cost: $    (120,000) 4) Related start up cost $              (5,000)     (60 Percent of Sales) -60% 5) Inventory increase $             25,000 11) Depreciation (Straight Line)/YR $      (60,000) 6) Accounts Payable...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR and PayBack Period 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $     200,000 2) New equipment cost $          (200,000) 9) Sales increase per year 4% 3) Equipment ship & install cost $            (25,000) 10) Operating cost: $    (120,000) 4) Related start up cost $              (5,000)     (60 Percent of Sales) -60% 5) Inventory increase $             25,000 11) Depreciation (Straight Line)/YR $      (60,000) 6) Accounts Payable...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR and PayBack Period 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $     200,000 2) New equipment cost $          (200,000) 9) Sales increase per year 4% 3) Equipment ship & install cost $            (25,000) 10) Operating cost: $    (120,000) 4) Related start up cost $              (5,000)     (60 Percent of Sales) -60% 5) Inventory increase $             25,000 11) Depreciation (Straight Line)/YR $      (60,000) 6) Accounts Payable...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
You are evaluating an investment project costing $11,800 initially. The project will provide $3,000 in after-tax...
You are evaluating an investment project costing $11,800 initially. The project will provide $3,000 in after-tax cash flows in the first year and $5,000 each year thereafter for 4 years. The maximum payback period for your company is 3 years. Your company's cost of capital is 14%. 1)What is the payback period for this project? 2)Should your company accept this project based on the payback period criterion? 3)What is the discounted payback period for this project? 4) Should your company...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
Year:           Project A      Project B         Project C     Product D       Project E
Year:           Project A      Project B         Project C     Product D       Project E 0                   (10,000) (15,000)         (20,000)       (50,000)          (100,000) 1                      4,000          8,000 7,000          10,000              33,000 2                      4,000 6,000 7,000          15,000              40,000 3                      4,000          4,000 7,000          (5,000)              33,000 4                       ------           2,000    7,000 20,000              40,000 5                       ------   -----    ------           10,000              (10,000) 6                       ------             ------ ------           (1,000) ------ 1. Calculate the payback of each project. 2. Calculate the discounted payback of each project (assume a cost-of-capital of 10 percent). 3. Calculate the NPV of each project (again, assume 10 percent). 4. Calculate the PI of each project (again, assume...