Question

You have to evaluate two mutually exclusive projects Alpha and Beta. Both projects have a cost...

You have to evaluate two mutually exclusive projects Alpha and Beta. Both projects have a cost fo capital is 12%. Both projects have an economic life of 5 years.

Project Alpha has a cost of $14,000. Its expected cash flows are an annuity of $4,500 per annum.

Project Beta has a cost of $14,000. It has one expected cash flow at the end of period 5 $30,000.

We must figure out the NPR, IRR and CHOICE for both Alpha and Beta.

Complete the following table:

Project:   NPR IRR CHOICE

Alpha-   

Beta-

Homework Answers

Answer #1

NPV is calculated by discounting the cashflows

PV = C/(1+r)^n

C - Cashflow

r - Discount rate

n - years to the cashflow

Project Alpha:

NPV = -14000 + 4500/(1+0.12)^1 + 4500/(1+0.12)^2 + 4500/(1+0.12)^3 + 4500/(1+0.12)^4 + 4500/(1+0.12)^5 = $2221.49

Project Beta:

NPV = -14000 + 30000/(1+0.12)^5 = $3022.81

Choose project Beta, as it has higher NPV

IRR is the rate at which NPV = 0

Project Alpha:

0 = -14000 + 4500/(1+IRR)^1 + 4500/(1+IRR)^2 + 4500/(1+IRR)^3 + 4500/(1+IRR)^4 + 4500/(1+IRR)^5

By trail and error, IRR = 18.23%

Project Beta

0 = -14000 + 30000/(1+IRR)^5

IRR = 16.47%

Choose project Alpha, as it has higher IRR.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000​) 1    30,000            00 2   30,000            00 3   30,000            00 4    30,000            00 5    30,000   210,000 If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? The NPV of Project B is $nothing.​(Round to the nearest​ cent.)
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of $37,000 today and is expected to generate cash flows of $31,000 for the next 4 years. Project Beta requires an initial investment of $92,000 and is expected to generate cash flows of $36,400 for the next 8 years. The cost of capital is 10%. The projects can be repeated with no change in cash flows. What is the NPV of the project that...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of 50,000 today and is expected to generate cash flows of 51,000 for the next 3 years. Project Beta requires an intial investment of 85,000 and is expected to generate cash flows of 49,700 for the next 6 years. The cost of capital is 6%. The projects can be repeated with no charge in cash flows. What is the NPV of the project that...
18) a firm needs to decide between two mutually exclusive projects. Porject Alpha requires an initial...
18) a firm needs to decide between two mutually exclusive projects. Porject Alpha requires an initial investment of $29,000 today and is expected to generate cash flow of $43,000 for the next 3 years. Project Beta requires an initial investment of $60,000 and is expected to generate cash flows of $45,000 for the next 6 years. The cost of capital is 11%. The projects can be repeated with no change in cash flows. What is the NPV of the project...
IRR: Mutually exclusive projects Ocean Pacific Restaurant is evaluating two mutually exclusive projects for expanding the...
IRR: Mutually exclusive projects Ocean Pacific Restaurant is evaluating two mutually exclusive projects for expanding the restaurant's seating capacity. The relevant cash flows for the projects are shown in the following table. The firm's cost of capital is 4%. Project X Project Y Initial Investment (CF) 980,000 363,000 Year               Cash inflows (CF) 1 150,000 110,000 2 170,000 98,000 3 220,000 93,000 4 270,000 82,000 5 340,000 67,000 a. calculate the IRR to the nearest whole percent for each of...
You are analyzing the following two mutually exclusive projects and have developed the following information. Please...
You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the crossover rate. Which project should you accept if the cost of capital is 5%, and which project should you accept if the cost of capital is 10%? Year Project A Cash Flow Project B Cash Flow 0 -$84,500 -$76,900 1 $29,000 $25,000 2 $40,000 $35,000 3 $27,000 $26,000 IRR A: ___________ IRR B: ___________ Crossover...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? A: Project B; it has a higher IRR and PI B: Neither project should be accepted, they both have negative NPVs C: Both project should be accepted; they have IRRs greater...
Projects A and B are mutually exclusive and both have an initial cost of $88,000. Project...
Projects A and B are mutually exclusive and both have an initial cost of $88,000. Project A has annual cash flows for three years of $18,300, $34,500, and $52,300, respectively. Project B has annual cash flows for three years of $26,400, $30,900, and $43,700. What is the crossover rate? Select one: a. 27.63 percent b. 25.30 percent c. 18.32 percent d. 13.33 percent e. 9.74 percent