Question

Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to...

  1. Dorati Inc. is considering two mutually exclusive projects.  Dorati used a 15% required rate of return to evaluate capital expenditure projects.  If the two projects have the costs and cash flows shown below, determine the NPV for each.

Year                             Project S                                   Project T

   0                                -$70,000                                   -$100,000

   1                                  $50,000                                      $60,000

   2                                  $60,000                                      $70,000

   3                                                                                    $80,000         

              4                                                                                    $90,000

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects are summarized below. Year ManBearPig Project Cash Flow Flying Car Cash Flow 0 -$100,000    -$200,000    1 25,000 50,000 2 25,000 50,000 3 50,000 80,000 4 50,000 100,000 The two projects have the same risk. At what cost of capital would the two projects have the same net present value (NPV)? A. 10.03% B. -24.45% C. 2.86% D. 13.04% E. 15.90%
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
The Mosco Manufacture is attempting to select the best of three mutually exclusive projects: X,Y, and...
The Mosco Manufacture is attempting to select the best of three mutually exclusive projects: X,Y, and Z. Although all the projects have 5-year lives, they possess differing degrees of risk. Project X is in class, V, the highest risk class; project Y is in class II, the below-average-risk class; project Z is in class III, the average-risk class. The basic cash flow data for each project and the risk classes and risk-adjusted discount rate (RADR) used by the firm are...
Kilroy, Inc. is considering two mutually exclusive projects. The cash flows of the projects are as...
Kilroy, Inc. is considering two mutually exclusive projects. The cash flows of the projects are as follows: Year Project A Project B 0 -$2,000,000 -$2,000,000 1 500,000 2 500,000 3 500,000 4 500,000 5 500,000 6 500,000 7 500,000 5,650,000 a. Compute the NPV and IRR for the above two projects, assuming a 13% required rate of return. NPV for project A= b. Discuss any potential conflict in evaluating these candidate projects. c. What decision should be made regarding these...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects are summarized below. Year ManBearPig Project Cash Flow Flying Car Cash Flow 0 -$100,000 -$200,000 1 25,000 50,000 2 25,000 50,000 3 50,000 80,000 4 50,000 100,000 What is the ManBearPig’s internal rate of return (IRR) at a 12% cost of capital? A. 12.7% B. 10.0% C. 14.6% D. 13.0% E. 15.9% Reddington Enterprises is considering the two capital budeting projects with the following...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -30,000 20,000 40,000 11,000   Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...
As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects with the following net cash flows:                               Project X               Project Z               Year       Cash Flow              Cash Flow               0              -$100,000             -$100,000               1                   50,000                  10,000               2                   40,000                  30,000               3                   30,000                  40,000               4                   10,000                  60,000 If Denver’s cost of capital is 15 percent, which project would you choose? Neither project. Project X, since it has the higher IRR. Project Z, since it has the higher NPV. Project X, since it has the higher NPV. Project Z, since it has the higher IRR....
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?20,000 10,000 30,000 1,000 Project B Cash Flow ?30,000 10,000 20,000 50,000 Use the MIRR decision rule to evaluate...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -21,000 11,000 31,000 2,000   Project B Cash Flow -31,000 11,000 21,000 51,000 Use the NPV decision rule to evaluate these...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT