Question

As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects...

As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects with the following net cash flows:
                              Project X               Project Z
              Year       Cash Flow              Cash Flow
              0              -$100,000             -$100,000
              1                   50,000                  10,000
              2                   40,000                  30,000
              3                   30,000                  40,000
              4                   10,000                  60,000

If Denver’s cost of capital is 15 percent, which project would you choose?

Neither project.

Project X, since it has the higher IRR.

Project Z, since it has the higher NPV.

Project X, since it has the higher NPV.

Project Z, since it has the higher IRR.

please help!!

Homework Answers

Answer #1

SEE THE IMAGE. ANY DOUBTS, FEEL FREE TO ASK. THUMBS UP PLEASE

WHEN PROJECTS ARE MUTUALLY EXCLUSIVE, WE PREFER THE PROJECT WITH HIGHEST POSITIVE NPV. HERE BOTH PROJECT HAVE NEGATIVE NPV.

SO NONE OF THEM IS TO BE SELECTED

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
5.  As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
5.  As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows.  The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? a.  Project X since it has higher IRR b.  Project Y since it has higher NPV c.  Project X since it has higher NPV d.  Neither project
5. As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive...
5. As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000​) 1    30,000            00 2   30,000            00 3   30,000            00 4    30,000            00 5    30,000   210,000 If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? The NPV of Project B is $nothing.​(Round to the nearest​ cent.)
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
A firm has the following investment alternatives. A firm has the following investment alternatives. Year    Project...
A firm has the following investment alternatives. A firm has the following investment alternatives. Year    Project A        Project B Cash Flow       Cash Flow               0        -$100,000        -$100,000   1            50,000              10,000   2            40,000              30,000   3            30,000              40,000   4            10,000              60,000 The firm's cost of capital is 7%. Project A and project B are mutually exclusive. Which investment(s) should the firm make? Project A because it has the higher IRR Project A because it has the higher NPV Neither because both have IRRs less than the cost of capital Project B...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)