Question

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 280,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.0 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 40% and the required rate of return is 10%.

a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

b. What is project NPV in the worst-case scenario? (A negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

Homework Answers

Answer #1
Most Likely Best Case Worst Case
Price $80 $84 $76
Variable cost $60 $57 $63
Fixed cost 280,000 266,000 294,000
Sales 30,000 31,500 28,500

Cash flow = [(1?T)×(revenue?cash expenses)] + (T×depreciation)Depreciation expense = $1 million/10 years = $100,000 per year

Best-case CF = 0.60×[31,500×($84?$57)?$266,000] + (0.40×$100,000) = $390,700

Worst-case CF = 0.60×[28,500×($76?$63)?$294,000] + (0.40×$100,000) = $85,900

10%, 10-year annuity factor =[1/0.10 - 1/(0.10*1.10^10] = 6.144567106

Best-case NPV = (6.144567106*$390,700) – $1,000,000 = $1,400,682

Worst-case NPV = (6.144567106*$85,900) – $1,000,000 = –$472,182

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 70 Variable cost: $ 50 Fixed cost: $ 200,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
Unit Price: $60, Variable Cost: $40, Fixed-Cost $420,000, Expected Sales: 47,000 Units per year However, you...
Unit Price: $60, Variable Cost: $40, Fixed-Cost $420,000, Expected Sales: 47,000 Units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is...
the mostly outcomes for a particular project are estimated as follows: Unit Price: $50 Variable Cost:...
the mostly outcomes for a particular project are estimated as follows: Unit Price: $50 Variable Cost: $30 Fixed Cost: $490000 Expected sales: 48000 units per year however, you recognize that some of the estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. the project will last for 10 years and require an initial investment of $2.3 million, which will be depreciated straight line over the...
You are considering a new product launch. The project will cost $740,000, have a 4-year life,...
You are considering a new product launch. The project will cost $740,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 430 units per year; price per unit will be $17,600, variable cost per unit will be $14,300, and fixed costs will be $710,000 per year. The required return on the project is 11 percent, and the relevant tax rate is 22 percent.    a. The unit sales, variable cost, and...
We are evaluating a project that costs $732,000, has a six-year life, and has no salvage...
We are evaluating a project that costs $732,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 55,000 units per year. Price per unit is $60, variable cost per unit is $30, and fixed costs are $640,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $735,200, has an eight-year life, and has no salvage...
We are evaluating a project that costs $735,200, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 80,000 units per year. Price per unit is $48, variable cost per unit is $33, and fixed costs are $730,000 per year. The tax rate is 22 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $560,400, has a six-year life, and has no salvage...
We are evaluating a project that costs $560,400, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 80,000 units per year. Price per unit is $38, variable cost per unit is $24, and fixed costs are $680,000 per year. The tax rate is 22 percent, and we require a return of 10 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $660,000, has a five-year life, and has no salvage...
We are evaluating a project that costs $660,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 69,000 units per year. Price per unit is $58, variable cost per unit is $38, and fixed costs are $660,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...