Exercise 10-8
Golden Industrial has estimated that production for the next five quarters will be:
Production Information | ||
1st quarter, 2017 | 50,000 units | |
2nd quarter, 2017 | 45,000 units | |
3rd quarter, 2017 | 54,000 units | |
4th quarter, 2017 | 44,000 units | |
1st quarter, 2018 | 52,000 units |
Prepare quarterly direct labor budgets for Golden Industrial for
2017. It takes 1 hour of direct labor to produce each finished unit
of product. Direct labor costs are $20 per hour. Each employee can
work 490 hours per quarter. (Round answers to 0 decimal
places, e.g. 125.)
Golden Industrial |
|||||||||||
Quarter 1 |
Quarter 2 |
Quarter 3 |
Quarter 4 |
Year |
|||||||
Total hoursLabor costApproximate number of employees neededAverage hours per quarterUnits to be producedLabor hours per unitLabor rate per hourLabor cost per unit |
|||||||||||
Labor rate per hourLabor hours per unitLabor cost per unitLabor costTotal hoursApproximate number of employees neededUnits to be producedAverage hours per quarter |
$ | $ | $ | $ | $ | ||||||
Labor cost per unitUnits to be producedLabor costLabor hours per unitTotal hoursApproximate number of employees neededAverage hours per quarterLabor rate per hour |
$ | $ | $ | $ | $ | ||||||
Approximate number of employees neededLabor cost per unitAverage hours per quarterLabor hours per unitLabor rate per hourUnits to be producedLabor costTotal hours |
|||||||||||
Labor rate per hourLabor hours per unitLabor costUnits to be producedTotal hoursAverage hours per quarterApproximate number of employees neededLabor cost per unit |
$ | $ | $ | $ | $ | ||||||
Labor cost per unitTotal hoursApproximate number of employees neededAverage hours per quarterLabor rate per hourLabor hours per unitUnits to be producedLabor cost |
|||||||||||
Average hours per quarterApproximate number of employees neededLabor cost per unitTotal hoursLabor hours per unitLabor rate per hourUnits to be producedLabor cost |
|||||||||||
Labor cost per unitAverage hours per quarterApproximate number of employees neededUnits to be producedLabor hours per unitLabor costLabor rate per hourTotal hours |
Direct labor hours required = Units produced * direct labor hours required per unit
Avereage number of employees required = Total hours required / Number of hours that an employee can work
Labor cost per unit = Hours required per unit * Labor cost per hour.
Please go through the following attachment for solution.