Question

cash flows per assessed outcomes cash flows. Taxes are not considered as this is assumed to...

cash flows per assessed outcomes cash flows. Taxes are not considered as this is assumed to be a not-for-profit business entity.

Pessimistic Most Likely Optimistic

Investment 80 80 80

Revenues 40 40 40

Costs 20 15 10

The revenues and costs occur in perpetuity. The cost of capital (WACC) for your project is 8 percent. Conduct a sensitivity analysis of the project's NPV to variations in costs base on the 3 outcomes above, that is Pessimistic, Most Likely, and Optimistic.

Homework Answers

Answer #1

NPV for a time period of n can be calculated using the formula: -C0+C1/(1+r)+C2/(1+r)^2+....Cn/(1+r)^n; where C is the initial investment, C1 to Cn are cash inflows and r is the required rate of return.

Given that cashflows are C for perpetuity. Present value of a cashflow of C till perpetuity with a discount rate of r is C/r.

So, NPV formula will become: NPV= -C0+ C/r.

Let us consider each scenario and calculate NPV for each one of them.

Pessimistic:

In Pessimistic Scenario, annual cashflows will be $40-$20= $20.

So, NPV= -80+ (20/8%)= -80+250= $170.

Most Likely:

In Most likely scenario, annual cashflows will be $40-$15= $25.

So, NPV= -80+ (25/8%)= -80+312.5= $232.50

Optimistic:

In Optimistic scenario, annual cashflows will be $40-$10= $30.

So, NPV= -80+ (30/8%)= -80+375= $295.

From the calculations, NPV is very sensitive to cost base. As expected cost decreases, NPV increases rapidly.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
If a project being considered has normal cash flows, with one outflow followed by a series...
If a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is CORRECT? A If a project's NPV is greater than zero, then its IRR must be less than the WACC. B If a project's NPV is greater than zero, then its IRR must be less than zero. C The higher the WACC used to calculate the NPV, the lower the calculated NPV will be. D A project's...
Project S costs $16,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $16,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,300 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Both Projects S and L, since both projects have IRR's > 0. c. Project...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $37,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Neither Project S nor L, since each project's NPV...
Project S costs $15,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $15,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $36,000 and its expected cash flows would be $13,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Project S, since the NPVS > NPVL. III. Neither S or L, since each project's NPV < 0....
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $38,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L, since the NPVL > NPVS. c. Both Projects S and L, since both projects have IRR's...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $35,000 and its expected cash flows would be $8,400 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $41,500 and its expected cash flows would be $10,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project S, since the NPVS > NPVL. c. Both Projects S and L,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT