Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $41,500 and its expected cash flows would be $10,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
S:
Present value of annuity=Annuity[1-(1+interest rate)^-time period]/rate
=7000[1-(1.14)^-5]/0.14
=7000*3.433080969
=$24031.57
NPV=Present value of inflows-Present value of outflows
=$24031.57-$13000
=$11031.57(Approx).
L:
Present value of annuity=Annuity[1-(1+interest rate)^-time period]/rate
=10500[1-(1.14)^-5]/0.14
=10500*3.433080969
=$36047.35
NPV=Present value of inflows-Present value of outflows
=$36047.35-$41500
=$(5452.65)(Approx).(Negative).
Hence S must be selected having higher NPV(Option B).
Get Answers For Free
Most questions answered within 1 hours.