Question

Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5...

Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $37,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend?

a. Project L, since the NPVL > NPVS.
b. Both Projects S and L, since both projects have NPV's > 0.
c. Neither Project S nor L, since each project's NPV < 0.
d. Both Projects S and L, since both projects have IRR's > 0.
e. Project S, since the NPVS > NPVL.

Homework Answers

Answer #1

The NPV is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

The NPV of Project S is computed as follows:

= - $ 14,000 + $ 6,500 / 1.131 + $ 6,500 / 1.132 + $ 6,500 / 1.133 + $ 6,500 / 1.134 + $ 6,500 / 1.135

= $ 8,862 Approximately

The NPV of Project L is computed as follows:

= - $ 37,500 + $ 14,700 / 1.131 + $ 14,700 / 1.132 + $ 14,700 / 1.133 + $ 14,700 / 1.134 + $ 14,700 / 1.135

= $ 14,203 Approximately

Since these two projects are mutually exclusive, hence we need to select the one which has the higher NPV. Since the NPV of project L is greater than the NPV of project S, hence Project L shall be accepted.

So, the correct answer is option a.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $38,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L, since the NPVL > NPVS. c. Both Projects S and L, since both projects have IRR's...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $35,000 and its expected cash flows would be $8,400 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $41,500 and its expected cash flows would be $10,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project S, since the NPVS > NPVL. c. Both Projects S and L,...
Project S costs $11,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $11,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $38,000 and its expected cash flows would be $13,300 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
Project S costs $15,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $15,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $36,000 and its expected cash flows would be $13,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Project S, since the NPVS > NPVL. III. Neither S or L, since each project's NPV < 0....
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Project...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....