Question

Consider a portfolio that is constituted by two projects, say A and B. Each project has...

Consider a portfolio that is constituted by two projects, say A and B. Each project has a 1/10 chance of a loss of $10 million and a 9/10 of a loss $1 million. Moreover, each project has probabilities 1/3 and 2/3 of a loss of $1 million and $10 million respectively, given that the other project had a loss of $1 million, and probabilities 1/4 and 3/4 of a loss of $1 million and $10 million respectively, given that the other project had a loss of $10 million. School of Economics MSc in Applied Economics and Finance & MSc in Finance and Banking Bank Supervision, Risk Management and Derivatives Professor: Plutarchos Sakellaris T.A.: Stelios Giannoulakis 2 (a) What is the 97.5% VaR for each project? (b) What is the 97.5% expected shortfall for each project? (c) What is the 97.5% VaR for the portfolio? (d) What is the 97.5% expected shortfall for the portfolio?

Homework Answers

Answer #1

a)

It is defined as the maximum dollar amount expected to be lost over a given time horizon, at a pre-defined confidence level. For example, if the 95% one-month VAR is $1 million, there is 95% confidence that over the next month the portfolio will not lose more than $1 million.

b)

When losses are not normally distributed, an expected shortfall with 97.5% confidence is liable to be quite a bit greater than VAR with 99% confidence. Expected shortfall in the FRTB is actually a stressed ES. It is to be calculated over the worst 250 days for the bank's current portfolio in recent memory

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
14.Each of two investment projects has a probability of 0.03 of a loss of $20 million...
14.Each of two investment projects has a probability of 0.03 of a loss of $20 million and a probability of 0.97 of a loss of $2 million during a one-year period. They are independent of each other. What are the 99% VaR and expected shortfall (ES) for a portfolio consisting of the two investments? VaR = $20 million; ES = $0.2362 million ($236,200) VaR = $22 million; ES = $23.62 million VaR = $20 million; ES = $23.62 million VaR...
You have two potential investment projects, Project A and Project B. You can take one, but...
You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are: Year 0 1 2 3 Project A Cash Flow -$50,000 $45,000 $5,000 $5,000 (respectively) Project B Cash Flow -$50,000 $5,000 $5,000 $50,000 (respectively). a) Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%. Which project would you take, and why? c) Compute...
You are constructing a portfolio of two assets, Asset A and Asset B. The expected returns...
You are constructing a portfolio of two assets, Asset A and Asset B. The expected returns of the assets are 10 percent and 16 percent, respectively. The standard deviations of the assets are 27 percent and 35 percent, respectively. The correlation between the two assets is .37 and the risk-free rate is 5.4 percent. What is the optimal Sharpe ratio in a portfolio of the two assets? What is the smallest expected loss for this portfolio over the coming year...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400,...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400, and $4,500 for Years 0 to 3, respectively. Project B has cash flows of −$10,000, $4,500, $3,400, and $5,100 for Years 0 to 3, respectively.          B-1 what is the IRR of project A?          B-2 What is the IRR of project B?          B-3 Based on the IRR rule, which project should be accepted and why?          B-4 At what required rate of...
13-2 a. Project X has an up-front cost of $20 million. The project is expected to...
13-2 a. Project X has an up-front cost of $20 million. The project is expected to produce after-tax cash flows of $7.5 million at the end of each of the next 3 years (t = 1, 2, and 3). The project has a WACC=10%. What is the project’s NPV? b. However, if the company waits a year they will find out more about the project’s expected cash flows. If they wait a year, there is a 50% chance the market...
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial...
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial outflow of $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,750 0.2 $          0   0.6   7,000 0.6 7,000   0.2   7,250 0.2 17,000   BPC has decided to evaluate the riskier project at 11% and the...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows of $30,000, $37,000, and $20,000 for Years 1 through 3, respectively. Project B produces cash inflows of $80,000 in Year 2 only. The required rate of return is 10 percent for Project A and 11 percent for Project B. Which project(s) should be accepted and why? Project A, because it has the higher required rate of return. Project A, because it has the larger...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,750...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,750 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $5,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 7,000 0.2 20,000 BPC has decided to evaluate the riskier project at an 11% rate...
eBook The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an...
eBook The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial outflow of $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,250 0.2 $          0   0.6   7,000 0.6 7,000   0.2   7,750 0.2 17,000   BPC has decided to evaluate the riskier project at 12% and...
Bradford Services Inc. (BSI) is considering a project that has a cost of $10 million and...
Bradford Services Inc. (BSI) is considering a project that has a cost of $10 million and an expected life of 3 years. There is a 30 percent probability of good conditions, in which case the project will provide a cash flow of $9 million at the end of each year for 3 years. There is a 40 percent probability of medium conditions, in which case the annual cash flows will be $4 million, and there is a 30 percent probability...