Question

A mass balance is performed for a treatment process consisting of a sedimentation tank followed by...

A mass balance is performed for a treatment process consisting of a sedimentation tank followed by a mixing tank. First, 25080 m3/d of raw wastewater with solids concentration of 180 mg/1 flows into the sedimentation tank. 80% of the incoming solids end up in the sludge. The effluent flows at a rate of 1040 m3/hr. Next, the effluent of the sedimentation tank enters the mixing tank where it is mixed with pure filtered water.
Assume that the density is the same for all streams.
Calculate the following:
a) Flow (m3/d) of the sludge in the sedimentation tank.
b) Solids concentration (mg/1) of the effluent in the sedimentation tank
c) Flow (m3/d) of the pure filtered water, knowing that that the final effluent of the mixing tank will be used in irrigation with a maximum solids concentration of 80 mgl.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process...
A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process followed by an activated sludge process composed of aeration tanks and a secondary clarifiers. This problem focuses on the activated sludge process. The activated sludge process receives a flow of 15 million gallons per day (MGD). The primary sedimentation process effluent has a BOD5 concentration of 180 mgBOD5/L (this concentration is often referred as S). Before flowing into the activated sludge process, the primary...
The town of Camp Verde has been directed to upgrade its primary Waste Water Treatment Plant...
The town of Camp Verde has been directed to upgrade its primary Waste Water Treatment Plant (WWTP) to a secondary plant that can meet an effluent standard of 25 mg/L BOD5 and 30 mg/L suspended solids. They have selected a completely mixed activated sludge system for the upgrade. The existing primary treatment plant has a flow rate of 0.029 m3/s. The effluent from the primary tank has a BOD5 of 240 mg/L. Using the following assumptions, estimate the required volume...
ANSWER as much as possible: Design an activated sludge process consisting of a complete mix flow...
ANSWER as much as possible: Design an activated sludge process consisting of a complete mix flow through aeration tank followed by final settling tanks. The sizing of the reactor and all appurtenances should be based on a solids retention time, (SRT), of 4 days and the particulates given below. Biological characteristics: Ks = 20 mg/L COD, kd = 0.1 per day, mumax = 3 gVSS/gVSS-day,    Y = 0.4 gVSS/gCOD Primary settling Tank Effluent Characteristics: Q= 20MGD, biodegradable COD, bCOD...
A completely mixed activated sludge process is designed to treat 20,000 m3 /d of domestic wastewater...
A completely mixed activated sludge process is designed to treat 20,000 m3 /d of domestic wastewater having a BOD5 concentration of 250 mg/L following primary treatment. The NPDES permit requirement for effluent BOD5 and TSS is 20 mg/L for each. The biokinetic parameters have been established as: yield = 0.6 , k = 5/d, Ks = 60 mg/L, and kd = 0.06/d. The MLVSS concentration in the aeration tank is to be maintained at 3000 mg/L and the ratio of...
Problem #3: Biochemical Oxygen Demand (BOD) and Stream Quality A wastewater treatment plant designed for a...
Problem #3: Biochemical Oxygen Demand (BOD) and Stream Quality A wastewater treatment plant designed for a community of 45,000 people has a flow of 100 gal/person/day and a BOD5 loading of 0.2 lb/person/day. The upstream characteristics of the receiving waters are: stream flow rate = 20 cfs and BOD5 = 2 mg/L The water quality standards require the in-stream BOD5 to be less than 7 mg/L in this stretch of the river. The minimum BOD removal efficiency that the treatment...
You have been retained to design a wastewater treatment plant using a conventional activated sludge process...
You have been retained to design a wastewater treatment plant using a conventional activated sludge process for a town of 40,000 people. The industrial flow contribution to the sewer system is 300,000 gallons per day. Effluent discharge standards require effluent BOD5 and total suspended solids concentration of <10 mg/l. Assume the following design criteria are applicable: Domestic sewage flow = 100 gal/cap/day (including I/I) BOD loading = 0.18 lbs/cap/day TSS loading = 0.20 lbs/cap/day BOD removal in primary = 33%...
You are tasked with conducting BOD studies for a waste treatment facility and its discharge to...
You are tasked with conducting BOD studies for a waste treatment facility and its discharge to a nearby river. You are told that the facility removes 93% of the BOD in total with a discharge rate of 1.0 m3 /s. you sample the receiving water and find that it has a 0.5 mg/L deficit from saturation concentration (saturation is at 9.7 mg/L) and a BOD5 content of 10 mg/L. The river flows at a speed of 0.25 m/s and has...
You are tasked with conducting BOD studies for a waste treatment facility and its discharge to...
You are tasked with conducting BOD studies for a waste treatment facility and its discharge to a nearby river. You are told that the facility removes 93% of the BOD in total with a discharge rate of 1.0 m3 /s. you sample the receiving water and find that it has a 0.5 mg/L deficit from saturation concentration (saturation is at 9.7 mg/L) and a BOD5 content of 10 mg/L. The river flows at a speed of 0.25 m/s and has...
Part I. Indicate whether true or false (T or F). ____ Storm water detention ponds typically...
Part I. Indicate whether true or false (T or F). ____ Storm water detention ponds typically are designed to regulate the outflow peak rate at or below a single target value, such as the pre-development (pre-land use change) peak runoff rate for a specified return period event. Detention storage alters the peak but not the volume of the outflow hydrograph. _____ Typical rating curves for weirs are concave upward. Typical rating curves for orifices are concave downward. ____ A sediment...