perform a differential benfit/cost anylysis to select the most economic system from the given two alternatives...

perform a differential benfit/cost anylysis to select the most economic system from the given two alternatives

alternative x y
initial cost 320 540
annual opertating cost 40 45
annual benefits 11 17
annual difbenefits 2 4
life in years 10 20

Homework Answers

Answer #1

Hence project x is more economical and suitable.

Enjoy and keep learning.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax...
Perform a present worth (PW)-based evaluation of the two alternatives below using a spreadsheet. The after-tax minimum acceptable rate of return (MARR) is 8% per year, Modified Accelerated Cost Recovery System (MACRS) depreciation applies, and Te = 40%. The (GI - OE) estimate is made for the first 3 years; it is zero in year 4 when each asset is sold. Alternative X Y First Cost, $ –8,000 –13,000 Salvage Value, Year 4, $ 0 2,000 GI-OE, $ per Year...
A company is considering 3 mutually exclusive alternatives along with "Do-Nothing" as part of a new...
A company is considering 3 mutually exclusive alternatives along with "Do-Nothing" as part of a new quality improvement initiative. The alternatives are in the table below. For each alternative, the salvage value at the end of the useful life is zero. At the end of 10 years, Alternative Z can be replaced by another Z with identical costs and benefits. If the MARR is 6.5 %, and the analysis period is 20 years, which alternative should be selected? X Y...
A firm is considering three mutually exclusive alternatives as part of a production improvement program.The alternatives...
A firm is considering three mutually exclusive alternatives as part of a production improvement program.The alternatives are: A   B C Installed cost $10,000 $15,000 $ 20,000 Annual benefit 1625 1530 1890   Useful life (Years) 10 20 20 The salvage value of each alternative is zero.At the end of 10 years Alternative A could be replaced with another A with identical cost and benefits . a)Which alternative should be selected if interest is 6% b)3% c)If there is a difference between...
Consider the three mutually exclusive alternatives below. At the end of their useful lives, Alternatives X...
Consider the three mutually exclusive alternatives below. At the end of their useful lives, Alternatives X and Z will be replaced with identical replacements so that a 10-year service requirement is met. If the MARR is 3% per year, which alternative (if any) should be chosen based on the annual worth method? Alt X Alt Y Alt Z Capital investment $300,000 $425,000. $500,000. Annual savings $68,750 $108,750. $188,750. Salvage value $90,000 $125,000. $140,000. Life, years 10 20 5
A company is evaluating the acquisition of a machine. The alternatives you have are two. The...
A company is evaluating the acquisition of a machine. The alternatives you have are two. The data is shown in the following table. Find the net present value of machine Y. (DISCOUNT RATE IS 10%) Concept Machine Y Initial Cost ($) - 46,000 Annual cost ($ / year) - 15,000 Salvage Value ($) 24,000 Life in years 3
One of two alternatives will be selected to reduce flood damage in a rural community in...
One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 5% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 3, 11, and 18 of the study period. Retention Pond Channel Initial Cost, $ 840,000...
The factory manager is considering the following two quotes from two vendors for purchase and maintanance...
The factory manager is considering the following two quotes from two vendors for purchase and maintanance of an equipment. Vendor​ X's estimates are all in actual​ dollars, while Vendor​ Y's estimates are all in​ year-zero dollars.      Vendor X                       Vendor Y Initial cost ​$9,200 ​$11,500 Annual cost ​$3,900 ​$3,000 Service life​ (yrs) 10 10 Salvage value ​$3,680 ​$4,600 The manager uses an annual real interest rate of 8​% for economic analysis. If inflation rate is expected to average 5.56% per year...
A firm must decide which one of the three alternatives below it should select to expand...
A firm must decide which one of the three alternatives below it should select to expand its capacity. The firm wishes a minimum annual profit of 20% of the initial cost of each separable increment of investment. Any money not invested in capacity expansion can be invested (forever) elsewhere for an annual yield of 20% of initial cost. Your reasoning must include the ∆IRR for each Challenger-Defender comparison. Alternative Initial Cost Annual Profit Profit Rate A $100,000 $30,000 30% B...
(TMAR) Do a rate of return analysis to select the most convenient alternative, if the company's...
(TMAR) Do a rate of return analysis to select the most convenient alternative, if the company's TMAR is 6% A B initial cost 8000 12000 operation annual cost 1400 900 salvage value 1000 2000 useful life 5 10
Two mutually exclusive alternatives (MEAs) are available to reduce potential earthquake damage at a government site....
Two mutually exclusive alternatives (MEAs) are available to reduce potential earthquake damage at a government site. The cash flow estimates for each alternative are shown below. The one-time repair costs occur in the middle of the period, that is, in year 10. Each MEA has a 20-year life. At an interest rate of 8% per year, determine the Benefit-to-Cost ratio (B/C) of the “increment.” Alternative One Alternative Two First Cost ($) -500,000 -1,100,000 Annual cost ($/year) -30,000 -40,000 One-time repair...