perform a differential benfit/cost anylysis to select the most economic system from the given two alternatives
alternative | x | y |
initial cost | 320 | 540 |
annual opertating cost | 40 | 45 |
annual benefits | 11 | 17 |
annual difbenefits | 2 | 4 |
life in years | 10 | 20 |
Hence project x is more economical and suitable.