Question

McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.  ...

McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.   However, while manufacturing the 1,000 units the microcomputer that contained the month's cost information broke down. With the computer out of commission, the accountant has been unable to complete the variance analysis report. The information missing from the report is lettered in the following set of data:

Variable overhead: Standard cost per unit: 0.4 labour hour at $4 per hour

Actual costs: $2,100 for 376 hours Flexible budget:  

a    Total flexible-budget variance:  

b    Variable overhead rate variance:

c    Variable overhead efficiency variance:  

d   Fixed overhead: Budgeted costs:  

e    Actual costs:  

f    Flexible-budget variance: $500 favourable Required: Compute the missing elements in the report represented by the lettered items.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Hollywood Jewellers planned to produce 1,800 necklaces during March with a total overhead budget of $49,600....
Hollywood Jewellers planned to produce 1,800 necklaces during March with a total overhead budget of $49,600. However, while manufacturing the 2,000th necklace the microcomputer that contained the month's cost information broke down. With the computer out of commission, the company has asked you to complete the variance analysis report. The missing information of the report is lettered in the following set of data: Variable overhead: Standard cost per necklace: 0.4 labour hour at $8 per hour Actual costs: $8,400 for...
Spooky Corporation had planned to produce 50,000 units of product during the first quarter of the...
Spooky Corporation had planned to produce 50,000 units of product during the first quarter of the current year. The company prepared the following budget on May 1: Budgeted (50,000 units) Variable costs: Direct materials used $ 36,000 Direct labor 45,000 Variable overhead 22,500 Fixed costs: Manufacturing overhead 58,500 Total manufacturing costs $ 162,000 During the first quarter, Spooky produced 60,000 units and incurred total manufacturing costs of $184,000. 1. Which of the following amounts should not be included in Spooky's...
Brodrick Company expects to produce 21,600 units for the year ending December 31. A flexible budget...
Brodrick Company expects to produce 21,600 units for the year ending December 31. A flexible budget for 21,600 units of production reflects sales of $626,400; variable costs of $64,800; and fixed costs of $141,000. QS 08-4 Flexible budget performance report LO P1 Assume that actual sales for the year are $752,500 (27,500 units), actual variable costs for the year are $113,100, and actual fixed costs for the year are $133,000. Prepare a flexible budget performance report for the year. (Indicate...
1) Determining Budgeted Overhead The overhead application rate for a company is $12 per unit, made...
1) Determining Budgeted Overhead The overhead application rate for a company is $12 per unit, made up of $7 per unit of fixed overhead and $5 per unit of variable over- head. Normal capacity is 10,000 units. In one month, there was a favorable flexible budget variance of $2,500. Actual overhead for the month was $110,000 and actual units produced were 15,125. Based on this information, determine the amount of the budgeted overhead for the actual level of production. 2)...
The Clark Company makes a single product and uses standard costing. Some data concerning this product...
The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow: Labour rate variance $7,000 favourable Labour efficiency variance $12,000 favourable Variable overhead efficiency variance $4,000 favourable Number of units produced 10,000 Standard labour rate per direct labour hour $12 Standard variable overhead rate per direct labour hour $4 Actual labour hours used 14,000 Actual variable manufacturing overhead costs $58,290 1) What was the variable overhead spending variance for...
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine       &n
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine         Machine-Hours   Overhead Costs            hour)  8,000    9,000    10,000 Variable costs   $1.05  $ 8,400 $ 9,450 $10,500 Fixed costs       24,800   24,800   24,800 Total Overhead Costs    $33,200 $34,250 $35,300 The following information is available for a recent period: a. The denominator activity of 8,000 machine-hours was chosen to compute the predetermined overhead rate. b. At the 8,000 standard machine-hours level of activity, the company should produce 3,200 units of product. c....
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Given the following information: Information Original Budget Actual Units produced 1,000 units 970 units Materials (kg)...
Given the following information: Information Original Budget Actual Units produced 1,000 units 970 units Materials (kg) 400 kg 415 kg Material Costs $8,000 See other info Direct Labour (Hours) 36,000 hours 34,010 hours Direct Labour Costs $385,000 $365,750 Variable Overhead Costs $255,000 $245,000 Fixed Overhead Costs $160,000 $165,000 Other Information Overhead is Allocated on Direct Labour Hours During the year, 500 kg of materials were purchased for $9,000 Beginning Inventory: 0kg Ending Inventory: 85kg Required: Calculate the following variances: Material...
Montgomery Company has developed the following flexible budget formulas for its four overhead items: Variable rate...
Montgomery Company has developed the following flexible budget formulas for its four overhead items: Variable rate per Overhead item Fixed Cost direct labor hour Maintenance $10,000 $3.00 Power $1,500 $0.30 Indirect labor cost $12.00 Equipment lease $7,000 Total $18,500 $15.30 Montgomery normally produces 15,000 units (each unit requires 0.30 direct labor hours); however this year 19,000 units were produced with the following actual costs: Overhead item Actual costs Maintenance $14,000 Power $2,200 Indirect labor cost $70,000 Equipment lease $7,000 Total...
Myers Company uses a flexible budget for manufacturing overhead based on direct labor hours. Variable manufacturing...
Myers Company uses a flexible budget for manufacturing overhead based on direct labor hours. Variable manufacturing overhead costs per direct labor hour are as follows. Indirect labor $1.10 Indirect materials 0.60 Utilities 0.40 Fixed overhead costs per month are Supervision $3,900, Depreciation $1,200, and Property Taxes $500. The company believes it will normally operate in a range of 7,400–11,300 direct labor hours per month. Assume that in July 2017, Myers Company incurs the following manufacturing overhead costs. Variable Costs Fixed...