Question

The Clark Company makes a single product and uses standard costing. Some data concerning this product...

The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow:

Labour rate variance $7,000 favourable
Labour efficiency variance $12,000 favourable
Variable overhead efficiency variance $4,000 favourable
Number of units produced 10,000
Standard labour rate per direct labour hour $12
Standard variable overhead rate per direct labour hour $4
Actual labour hours used 14,000
Actual variable manufacturing overhead costs $58,290

1)

What was the variable overhead spending variance for May?

Multiple Choice

  • $1,710 favourable.

  • $1,710 unfavourable.

  • $2,290 favourable.

  • $2,290 unfavourable.

2)

What was the actual direct labour rate for May in dollars per hour?

Multiple Choice

  • $11.50.

  • $11.75.

  • $12.00.

  • $12.50.

3)

What was the total standard cost for direct labour for May?

Multiple Choice

  • $120,000.

  • $161,000.

  • $168,000.

  • $180,000

4)

What was the total standard cost for variable overhead for May?

Multiple Choice

  • $40,000.

  • $50,000.

  • $56,000.

  • $60,000.

5)

What are the standard hours allowed to make one unit of finished product?

Multiple Choice

  • 1.0 hours.

  • 1.2 hours.

  • 1.5 hours.

  • 2.0 hours.

Homework Answers

Answer #1

1. Variable overhead spending variance = (Actual hours * Actual rate) - (Actual hours * Standard rate)

= $58,290 - (14,000 * $4)

= $2,290 Unfavorable

2. Labor rate variance = (Actual hours * Actual rate) - (Actual hours * Standard rate)

$(7,000) = (14,000 * Actual rate) - (14,000 * $12)

Actual rate = $11.5

3. Labor efficiency variance = (Actual hours * Standard rate) - (Standard hours * Standard rate)

$(12,000) = (14,000 * $12) - (Standard hours * Standard rate)

Standard cost = $180,000

4. Variable overhead efficiency variance = (Actual hours * Standard rate) - (Standard hours * Standard rate)

$(4,000) = $58,290 - (Standard hours * Standard rate)

Standard cost = $62,290

5. Labor efficiency variance = [(Actual hours * Standard rate) - (Standard hours * Standard rate)] / 10,000

$(12,000) = [(14,000 * $12) - (Standard hours * $12)] / 10,000

Standard hours = 15,000 / 10,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
The following standards for variable manufacturing overhead have been established for a company that makes only...
The following standards for variable manufacturing overhead have been established for a company that makes only one product: Standard hours per unit of output 7.8 hours Standard variable overhead rate $12.55 per hour The following data pertain to operations for the last month: Actual hours 2,900 hours Actual total variable overhead cost $36,975 Actual output 200 units What was the variable overhead efficiency variance for the month? Multiple Choice $580 unfavourable. $17,397 unfavourable. $16,817 unfavourable. $0.
Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per...
Juliet Pants standard cost per pants included 0.20 direct labour hours per pants at $16.00 per hour. Juliet Pants actually used 10,350 direct labour hours at a cost of $15.80 per hour to produce 50,000 pants. a) Calculate the direct labour rate variance: $ b) Is the direct labour rate variance favourable or unfavourable? c) Calculate the direct labour efficiency variance: $ d) Is the direct labour efficiency variance favourable or unfavourable? e) Calculate the total direct labour variance: $...
Tractor Corporation produces toy tractors. The company uses the following direct cost categories: Category Standard Inputs...
Tractor Corporation produces toy tractors. The company uses the following direct cost categories: Category Standard Inputs for 1 output Std. Cost per input Direct Materials 4.00 $12.50 Direct Labour 1.40 9.50 Direct Marketing 0.54 5.50 Actual performance and budgeted performance for the company is shown below: Actual output: (in units) 5,000 Direct Materials: Materials costs $299,000 Input purchased and used 23,000 Actual price per input $13.00 Direct Manufacturing Labour: Labour costs $ 95,000 Labour-hours of input 9,500 Actual price per...
Lime Corporation makes a product with the following standard costs: Input Standard Quantity or Hours Standard...
Lime Corporation makes a product with the following standard costs: Input Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 9.5 grams $6.00 per gram $57.00 Direct labor 0.5 hours $23.00 per hour $11.50 Variable overhead 0.5 hours $2.00 per hour $1.00 In November the company's budgeted production was 3,000 units but the actual production and sales was 2,800 units. The company used 27,670 grams of the direct material and 1,390 direct labor-hours to produce...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour...
Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Planned production—units 50 000 Direct labour hours 200 000 Variable overhead $ 1 000 000 Fixed overhead $ 600 000 The following were the actual results Actual production—units 48 000 Direct labour hours 195 000 Variable overhead $ 950 000 Fixed overhead $ 610 000 Calculate the...
Smyer Corporation makes a product with the following standard costs: Smyer Corporation makes a product with...
Smyer Corporation makes a product with the following standard costs: Smyer Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 6.9 pounds $14.00 per pound $96.60 Direct labor 2.8 hours $18.00 per hour $ 50.40 Variable overhead 2.8 hours $ 7.00 per hour $ 19.60 The company reported the following results concerning this product in July. Originally budgeted output 6,700 units Actual output 6,410 units Raw...
Requirement: 1 Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours...
Requirement: 1 Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 6.4 ounces $ 3.00 per ounce $ 19.20 Direct labor 0.7 hours $ 19.00 per hour $ 13.30 Variable overhead 0.7 hours $ 3.00 per hour $ 2.10 The company reported the following results concerning this product in February. Originally budgeted output 4,700 units Actual output 5,200 units Raw materials used in production 30,400...
Doogan Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...
Doogan Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Direct materials 2.0 grams $ 7.00 per gram Direct labor 1.6 hours $ 14.00 per hour Variable overhead 1.6 hours $ 2.00 per hour The company produced 4,600 units in January using 10,220 grams of direct material and 2,200 direct labor-hours. During the month, the company purchased 10,790 grams of the direct material at $7.40 per gram. The actual direct labor rate...
Question 1 A company manufactures a single product for which the standard variable cost is:                            
Question 1 A company manufactures a single product for which the standard variable cost is:                                                                          K per unit Direct material: 81 kg x K7 per kg                            567 Direct labour:    97 hours x K8 per hour                   776 Variable overhead: 97 hours x K3 per hour              291                                                                                1,634 Budget Sales and production volume                   81,600 units Standard selling price                               K59 per unit Standard variable cost                             K24 per unit During January, 530 units were produced and the costs incurred were as follows:...