The cost associated with estimating a project would be included in the calculation of
a |
Office Overhead. |
b |
the work estimate. |
c |
Project Overhead. |
d |
Division 0 Costs. |
The cost associated with estimating a project would be included in the calculation of
a. Office Overhead.
b. the work estimate.
c. Project Overhead.
d. Division 0 Costs.
The cost of estimating a project would be included in the calculation of Project Overhead.
Overhead allocation is the best method for allocation of cost that are of general nature and doesn't relate to a single activity. Estimating cost, being general in nature, will be included in the calculation of Project Overhead.