Question

Which of the following would not be included in the cost summary on a job cost...

Which of the following would not be included in the cost summary on a job cost sheet?

Direct labor costs for the job

Marketing costs for the job

Manufacturing overhead costs for the job

Direct materials costs for the job

Homework Answers

Answer #1

Answer: Marketing costs for the job is not be included in the cost summary on a job cost sheet.since this is not a manufacturing cost.

Job cost sheet is a document which is used for record of manufacturing cost and is prepared by companies that use job order costing system to calculate and allocate cost to product and services And Direct labor costs for the job, Manufacturing overhead costs for the job and Direct materials costs for the job will be include in the job cost sheet,since these are manufacturing cost.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,000 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 480 22 300 360 24 1,640 27 1,560 31 700 840 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost (a) Answer the following questions. (1)...
Job 652 was recently completed. The following data have been recorded on its job cost sheet....
Job 652 was recently completed. The following data have been recorded on its job cost sheet. Direct materials=$59,900 Direct labor-hours=1,225 DLHs Direct labor wage rate= $14 per DLH Number of units completed=3,700 The company applies manufacturing overhead on the basis of direct labor hours. The predetermined overhead rate is $32 per direct labor hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round answer to 2 decimal places.) Unit product cost=????
Cullumber Company is working on two job orders. The job cost sheets show the following. Job...
Cullumber Company is working on two job orders. The job cost sheets show the following. Job 201 Job 202 Direct materials $7,350 $8,950 Direct labor 4,300 8,250 Manufacturing overhead 5,200 9,950 Prepare the three summary entries to record the assignment of costs to Work in Process from the data on the job cost sheets. (Credit account titles are automatically indented when amount is entered. Do not indent manually.) No. Account Titles and Explanation Debit Credit (a) (To assign materials to...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
Job 652 was recently completed. The following data have been recorded on its job cost sheet:...
Job 652 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 61,900 Direct labor-hours 1,229 DLHs Direct labor wage rate $ 12 per DLH Number of units completed 4,100 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $36 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
The following data have been recorded for recently completed Job 674 on its job cost sheet....
The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,102. A total of 41 direct labor-hours and 197 machine-hours were worked on the job. The direct labor wage rate is $23 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $25 per machine-hour. The total cost for the job on its job cost sheet would be: Multiple Choice $4,926 $10,115 $7,970...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:        Direct materials        Direct labor         Manufacturing overhead      Total cost      Unit cost (1) What are the source documents for direct materials, direct labor, and...
Job 243 was recently completed. The following data have been recorded on its job cost sheet:...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 49,370 Direct labor-hours 410 labor-hours Direct labor wage rate $ 12 per labor-hour Machine-hours 491 machine-hours Number of units completed 2,800 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
Assigning Overhead To A Job Beta Corp. applies overhead to jobs on the basis of direct...
Assigning Overhead To A Job Beta Corp. applies overhead to jobs on the basis of direct labor costs. Job X which was started and completed during the current period shows charges of $10,000 for direct materials, $16,000 for direct labor, and $12,000 for overhead on its job cost sheet. Job Y which still was in process at year end shows charges of $5,000 for direct materials, and $8,000 for direct labor. Required: Should any overhead cost be applied to Job...
Job 31 has a direct materials cost of $400 and a total manufacturing cost of $1,300....
Job 31 has a direct materials cost of $400 and a total manufacturing cost of $1,300. Overhead is applied to jobs at a rate of 200 percent of direct labor cost. Use the relationships among total manufacturing costs, conversion cost, and prime cost to determine the following costs for job 31: a. conversion costs b. direct labor cost c. manufacturing overhead costs d. prime costs
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT