Question

Job A3B was ordered by a customer on September 25. During the month of September, Jaycee...

Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,300 of direct materials and used $4,800 of direct labor. The job was not finished by the end of the month, but needed an additional $3,800 of direct materials and additional direct labor of $8,100 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the balance in the Work in Process account at the end of September relative to Job A3B?

Multiple Choice

  • $11,900

  • $17,700

  • $7,100

  • $12,900

  • $8,100

Homework Answers

Answer #1

Correct answer-------------$17,700

Working

Direct material Direct labor Overhead applied (4800 x 200%) Total
Beginning Wip cost $             3,300.00 $             4,800.00 $             9,600.00 $           17,700.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee...
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred....
Job 83B was ordered by customer on September 25 during the month of September Jayci Corporation...
Job 83B was ordered by customer on September 25 during the month of September Jayci Corporation requisitioned $2500 of direct Materials and used $4000 of direct labor the job is not finished by the end of September but need an additional $6500 to finish the job the company applies overhead at the end of each month at a rate of 200% of the direct labor costs what is the amount of job cost added to work in process inventory during...
1. The overhead cost applied to a job during a period is recorded with a credit...
1. The overhead cost applied to a job during a period is recorded with a credit to Factory Overhead and a debit to: Multiple Choice Jobs Overhead Expense. Cost of Goods Sold. Finished Goods Inventory. Indirect Labor. Work in Process Inventory. 2. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the...
10-Dazzle, Inc. produces beads for jewelry making use. The following information summarizes production operations for June....
10-Dazzle, Inc. produces beads for jewelry making use. The following information summarizes production operations for June. The journal entry to record June production activities for direct material usage is: Direct materials used $ 90,000 Direct labor used 163,000 Predetermined overhead rate (based on direct labor) 155 % Goods transferred to finished goods 435,000 Cost of goods sold 447,000 Credit sales 813,000 Multiple Choice Debit Work in Process Inventory $90,000; credit Raw Materials Inventory $90,000. Debit Work in Process Inventory $90,000;...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $8,500, direct labor of $3,800, and applied overhead of $3,230. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on account) for $25,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 93,000 and estimated factory overhead is $511,500. The following information is for September of the current year. Job A was completed during September, and Job B was started but not finished September 1, inventories        Materials inventory $ 8,400    Work-in-process inventory (All Job A) 33,000    Finished goods...
Badour Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct...
Badour Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours were 128,000 and estimated factory overhead was $960,000. The following information was for September. Job X was completed during September, while Job Y was started but not finished. September 1, inventories: Materials $ 10,500 Work-in-process (All Job X) 38,800 Finished goods 81,800 Materials purchases $ 139,000 Direct materials...
Turco Products uses a job order cost system. The following debits (credits) appeared in Work-in-Process Inventory...
Turco Products uses a job order cost system. The following debits (credits) appeared in Work-in-Process Inventory for September: Description Amount September 1 Balance $ 27,400 For the month Direct materials 162,800 For the month Direct labor 101,700 For the month Factory overhead 82,377 For the month To finished goods ( 318,400 ) Turco applies overhead to production at a predetermined rate of 81 percent based on direct labor cost. Job 9-27, the only job still in process at the end...
Yurman Inc. uses a job-order costing system. During the month of May, the following transactions occurred:...
Yurman Inc. uses a job-order costing system. During the month of May, the following transactions occurred: May 1 Purchased materials on account for $29,680. 3 Requisitioned materials totaling $24,480 for use in production. Of the total, $9,220 was for Job 58, $8,940 for Job 59, and the remainder for Job 60. 31 Incurred direct labor for the month of $28,800, with an average wage of $16 per hour. Job 58 used 790 hours; Job 59, 590 hours; and Job 60,...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 150,000 and estimated factory overhead is $1,140,000. The following information is for September. Job X was completed during September, while Job Y was started but not finished. September 1, inventories: Materials $ 25,700 Work-in-process (All Job X) 55,100 Finished goods 107,300 Materials purchases $ 174,000 Direct materials...