Question

Triple C Ltd. is in the business of manufacturing cabinets, computer stands, and countertops. Most of...

Triple C Ltd. is in the business of manufacturing cabinets, computer stands, and countertops. Most of its jobs are contracts for home builders. The following information is available for the month of July:

Costs Incurred
to July 1
Added in July
Job
Number
Direct
Materials
Direct
Labour
Direct
Materials
Direct
Labour
Status at July 31
101 $9,000 $2,000 $ 0 $1,000 Completed but not sold
103 2,500 1,500 ? ? Not completed
111 600 100 500 3,000 Completed but not sold
115 800 200 Not completed


Activity in accounts:

Opening Account Balance
July 1
Purchased
in July
Issued/Used
in July
Ending
Balance July 31
Direct Materials $3,000 $6,000 $4,900 $ ?
Direct Labour 8,000


On July 1, finished goods inventory consisted of one job, 105, with a total cost of $18,000. This job was sold during July.

(Note: Manufacturing overhead is applied at 120% of the direct labour cost.)

Calculate the costs of completed jobs 101 and 111 as at July 31.

Job 101 Job 111
Completed job costs $ $

Homework Answers

Answer #1

Please find below table useful to compute desired results: -

End results would be as follows: -

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 6,600 102 5,280 103 960 $ 3,600 104 4,080 7,200 105 8,400 106 2,900 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
At the end of June, Victory Manufacturing Inc. had $24,000 of raw materials on hand. During...
At the end of June, Victory Manufacturing Inc. had $24,000 of raw materials on hand. During the month, the company worked on three jobs. At the end of June, Job 123 was complete and ready to be shipped to the customer, while Jobs 124 and 125 were both in process. As of June 30th, the Job Cost Sheets for the three jobs reported the following: Job 123 Job 124 Job 125 Direct materials $60,000 $24,000 $72,000 Direct labour $18,000 $6,000...
A company began operations on January 1, 20x3. The company uses a job order system and...
A company began operations on January 1, 20x3. The company uses a job order system and started the following jobs during January 20x3: Job 101 Job 102 Job 103 Direct materials $18422 $24413 $35988 Direct labour hours 971 1387 737 Additional information is as follows: Total estimated overhead $302539 Total estimated direct labour hours 19248 Actual direct labour rate $19 per direct labour hour All three jobs were completed by the end of January 20x3. Finished goods at January 31,...
Golden Heaven Ltd. Manufactures custom kitchen cabinets and uses a job costing system. On January 1,...
Golden Heaven Ltd. Manufactures custom kitchen cabinets and uses a job costing system. On January 1, 2015, there were no balances in work-in-process or finished goods inventories. The following events occurred in January 2015: 1. The company began two jobs: Job CC456 (comprising 40 tables) and Job DD789 (comprising 60 chairs). 2. 400 square metres of timber were purchased at a total cost of $5,800. 3. 80 litres of glue were purchased at a cost of $6 per litre. 4....
Problem 1 (14 marks) (28 minutes) Cicero Company uses a job-order costing system that uses a...
Problem 1 (28 minutes) Cicero Company uses a job-order costing system that uses a plantwide overhead rate based on direct labour hours. Estimated information for the year is as follows: Overhead $665,000 Direct labour hours 100,000 There was one job in finished goods inventory at the beginning of July: Job 209 Direct materials $18,500 Direct labour cost 37,500 Direct labour hours 2,500 Cicero worked on five jobs in July. Data are as follows: Job 210 Job 211 Job 212 Job...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Partially completed job sheets for Freeley Co. appear below. These are the only jobs this company...
Partially completed job sheets for Freeley Co. appear below. These are the only jobs this company has. (SEND YOUR WORK) Job 10 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $6,000 $8,000 $10,000 7/12 $15,000 7/19 $20,000 7/26 $10,000 7/29 $5,000 Job 11 Date Direct Materials Direct Labor Manufacturing Overhead Total 7/1 Beginning Balance $3,000 $6,000 $7,500 7/5 $8,000 7/15 $9,000 7/20 $7,000 7/31 $14,000 Job 10 was completed on July 29, 2020. What was the July...
Waldbauer Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed...
Waldbauer Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. In October the company completed job N66B that consisted of 10,000 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job N66B shows the following costs: Beginning balance $ 41,000 Direct materials $251,000 Direct labor cost $ 98,000 Manufacturing...
Milner Manufacturing uses a job-order costing system. On May 1, the company has a total balance...
Milner Manufacturing uses a job-order costing system. On May 1, the company has a total balance in Work in Process Inventory of $3,200 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,200. During May, a summary of source documents reveals the following: Job Number Materials Requisition Slips Labour Time Tickets 429 $2,500 $2,200 430 $3,600 $3,000 431 $4,400 $10,500 $7,600 $12,800 General use costs incurred in month $1,000 $1,500 $11,500 $14,300 Milner Manufacturing applies manufacturing...