Question

On 1 January 2019, 3D-Construction (Pty) Ltd obtained planning permission to build a new office building....

On 1 January 2019, 3D-Construction (Pty) Ltd obtained planning permission to build a new office building. Construction commenced on 1 March 2019. To help fund the cost of this building, a loan for $10 million was taken out from Bank Gaborone on 1 April 2019. The interest rate on the loan was 10% per annum. Construction of the building ceased during the month of July due to an unexpected shortage of labor and materials. By 31 December 2019, the building was not complete. Costs incurred to date were $24 million (excluding interest on the loan).

Required: Discuss the accounting treatment of the above in the financial statements of 3D-Construction for the year ended 31 December 2019.

Homework Answers

Answer #1

Accounting treatment of the given costs are as under:

Loan of $10 Million Dollar - As loan is outstanding as on 31st Dec 2019, we will show this amount as liability.

Interest on $10 Million Dollar at 10% for 10 months - Assuming interest amount is not paid. The same will be added in Loan outstading amount as on 31st Dec 2019.

Stoppage in Construction - Since Stopage of work occuring due to unexpected shortage of labour and material, the same will not be capitalised in the books. And the cost incurred during stoppage period will be written off in Profit & Loss A/c

Cost of Construction - Contruction cost including interest expenses on loan till 31st Dec 2019 will be capitalised in the books except cost and interest expense incurred during stoppage period

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,820,000 March 1, 2018 1,440,000 June 30, 2018 1,640,000 October 1, 2018 1,440,000 January 31, 2019 396,000 April 30, 2019 729,000 August 31, 2019 1,026,000 On January 1, 2018, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work...
On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work commenced on June 1, 2018, and it is expected to continue through May 31, 2019. Powell made progress payments to the contractor in 2018 as follows: Date Amount June 1 $  123,000 July 1 174,000 September 1 81,000 November 1     33,000 $411,000 As stated previously, Powell took a 1-year, 8%, $175,000 construction loan to help fund the work on this project. The company also has...
On January 1, 2018, ABC Company began construction of a building to be used as its...
On January 1, 2018, ABC Company began construction of a building to be used as its warehouse. The building was completed on November 1, 2019. Expenditures for the project during 2018 were as follows: January 1, 2018 900,000 April 1, 2018 700,000 July 1, 2018 650,000 October 1, 2018 840,000 On January 1, 2018, ABC Company obtained a $4,000,000 construction loan with 9% interest rate payable in 5 years. The Company’s other debts included a note of $1,000,000 at 11%...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
WildhorseFurniture Company started construction of a combination office and warehouse building for its own use at...
WildhorseFurniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $11,000,000 on January 1, 2020. Wildhorse expected to complete the building by December 31, 2020. Wildhorse has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $4,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,080,000 Long-term loan-11% interest, payable on January 1 of each...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2019 $3,400,000 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,380,000 Long-term loan-9% interest, payable on January 1 of...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
Splish Furniture Company started construction of a combination office and warehouse building for its own use...
Splish Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,500,000 on January 1, 2020. Splish expected to complete the building by December 31, 2020. Splish has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,400,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,780,000 Long-term loan-11% interest, payable on January 1 of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT