Question

On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work...

On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work commenced on June 1, 2018, and it is expected to continue through May 31, 2019. Powell made progress payments to the contractor in 2018 as follows:

Date

Amount

June 1

$  123,000

July 1

174,000

September 1

81,000

November 1

    33,000

$411,000

As stated previously, Powell took a 1-year, 8%, $175,000 construction loan to help fund the work on this project. The company also has a 4-year, 5%, $654,350 loan that is not related to the construction project.

Give the adjusting entry needed at December 31, 2018 to record the capitalization of interest for this project.

Homework Answers

Answer #1
Calculation of Avoidable Interest Weighted Average expenditure Rate Avoidable Interest
Calculate interest on loan specifically for construction 175,000 8% 14000 Date Amount
Calculate interest on remaining loan up to weighted
average expense
119,000 5% 5950 1-Jun 123,000 102500
294000 19950 1-Jul 174,000 130500
1-Sep 81,000 47250
a The avoidable interest on this project $19,950 1-Nov 33,000 13750
Weighted cost 294000
Account Title and Explanation Debit Credit
Warehouse Building 19950
Interest Payable 19950
(To record adjusting entry)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 430,000 September 30, 2018 630,000 November 30, 2018 630,000 January 30, 2019 570,000 The company’s fiscal year-end is December 31. Required: Calculate...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 328,000 September 1, 2018 $ 486,000 December 31, 2018 $ 486,000 March 31, 2019 $ 486,000 September 30, 2019 $ 328,000 Dreamworld had $6,200,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 343,000 September 1, 2018 $ 501,000 December 31, 2018 $ 501,000 March 31, 2019 $ 501,000 September 30, 2019 $ 343,000 Dreamworld had $6,700,000 in 14% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $6,000,000, 8% note $9,000,000, 3% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 580,000 September 30, 2018 870,000 November 30, 2018 870,000 January 30, 2019 810,000 The company’s fiscal year-end is December 31. Required: Calculate...
On January 1, 2018, ABC Company began construction of a building to be used as its...
On January 1, 2018, ABC Company began construction of a building to be used as its warehouse. The building was completed on November 1, 2019. Expenditures for the project during 2018 were as follows: January 1, 2018 900,000 April 1, 2018 700,000 July 1, 2018 650,000 October 1, 2018 840,000 On January 1, 2018, ABC Company obtained a $4,000,000 construction loan with 9% interest rate payable in 5 years. The Company’s other debts included a note of $1,000,000 at 11%...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
Stephenson Inc. began to construct a building for its use on January 1, 2018. All costs...
Stephenson Inc. began to construct a building for its use on January 1, 2018. All costs associated with the construction are being debited to an account called “Construction-in-Progress.” The construction will take approximately 24 months. Weighted-average expenditures for 2018 have already been determined to be $1,800,000. The company has one specific as well as two non-specific loan borrowings. Details are as follows: Specific Loan Borrowing: $1,000,000 loan at 12% taken out 1/1/2018 and due in 2019. Non-specific Borrowings: Note #1:...