Question

Crane Landscaping began construction of a new plant on December 1, 2017. On this date, the...

Crane Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $140,400 in cash. In addition, it paid $2,640 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $1,200 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $34,800. The necessary building permits costing $3,120 were obtained from the city and paid for on December 1 as well. The excavation work began during the first week in December with payments made to the contractor in 2018 as follows. Date of Payment Amount of Payment March 1 $252,000 May 1 332,400 July 1 64,800 The building was completed on July 1, 2018. To finance construction of this plant, Crane borrowed $609,600 from the bank on December 1, 2017. Crane had no other borrowings. The $609,600 was a 10-year loan bearing interest at 9%. Compute the balance in each of the following accounts at December 31, 2017, and December 31, 2018. (Round answers to 0 decimal places, e.g. 5,275.) December 31, 2017 December 31, 2018 (a) Balance in Land Account (b) Balance in Building (c) Balance in Interest Expense

Homework Answers

Answer #1
T-Accounts:
DR CR BAL calculation
LAND A/C
12/1/2017 PURCHASE 140400
SURVEY 2640
INSUR 3840
MATERIAL 1200
12/31/2017 CLOSING BAL 145680
BUILDING A/C
12/1/2017 ARCHITECT 34800
PERMIT 3120
12/31/2017 CLOSING BAL 37920
3/1/2018 CONTRACTOR 252000
5/1/2018 CONTRACTOR 332400
7/1/2018 CONTRACTOR 64800
12/31/2018 CLOSING BAL 687120
INTEREST A/C
12/31/2017 FINANCE CO. 1377 1377 (145680+34800+3120)*9%*1/12
12/31/2018 FINANCE CO. 45864 47241 (183600*9%)+(252000*9%*10/12)+(174000*9%*8/12)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Culver Landscaping began construction of a new plant on December 1, 2017. On this date, the...
Culver Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $148,800 in cash. In addition, it paid $1,920 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $39,600. The necessary...
Crane Company is constructing a building. Construction began on February 1 and was completed on December...
Crane Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $5,220,000 on March 1, $3,480,000 on June 1, and $8,700,000 on December 31. Crane Company borrowed $2,900,000 on March 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 14%, 5-year, $5,800,000 note payable and an 11%, 4-year, $10,150,000 note payable. Compute avoidable interest for Crane Company. Use the...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
Problem 10-1 At December 31, 2016, certain accounts included in the property, plant, and equipment section...
Problem 10-1 At December 31, 2016, certain accounts included in the property, plant, and equipment section of Monty Company’s balance sheet had the following balances. Land $239,000 Buildings 901,400 Leasehold improvements 660,000 Equipment 882,000 During 2017, the following transactions occurred. 1. Land site number 621 was acquired for $859,100. In addition, to acquire the land Monty paid a $51,100 commission to a real estate agent. Costs of $44,400 were incurred to clear the land. During the course of clearing the...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 72 October 1, 2020 40 February 1, 2021 48 April 1, 2021 30 September 1, 2021 29 October 1, 2021 15 On July 1, 2020, Crocus obtained a $88 million construction loan with a 10% interest rate. The loan was outstanding through the end of...
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December...
The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December 31, 2017: Plant Asset Accumulated Depreciation Land $ 400,000 $ — Land improvements 205,000 50,000 Building 1,750,000 355,000 Machinery and equipment 1,168,000 410,000 Automobiles 175,000 117,000 Transactions during 2018 were as follows: On January 2, 2018, machinery and equipment were purchased at a total invoice cost of $285,000, which included a $6,000 charge for freight. Installation costs of $32,000 were incurred. On March 31,...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use. To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation...
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation purchased a parcel of land as a factory site for $185,000. An old building on the property was demolished and construction began on a new warehouse that was completed on October 15, 2018. Costs incurred on the construction project are listed below.                Cost of building construction…………………………………          $620,000                Title insurance…………………………………………………               1,500                Cost of constructing a driveway……………………………….               8,000                Legal fees to purchase...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...