Question

XYZ Corp began construction on a building on January 1, 2016. On that date, it made...

XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use.

To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding that was not specifically related to the construction project. Both Notes were outstanding for the entire construction project.

What are the weighted average accumulated expenditures on the construction project?

Homework Answers

Answer #1

Weighted Average accumulated expenditures

Weighted average accumulated expenditure is the amounts incurred on construction during the period multiplied by number of months remain in that period.

And it is calculated to calculate the amount of interest to be capitalized on self-construction assets

1. Calculation of weighted average accumulated expenditures

Period of Contract = January 1, 2016 –December 31, 2016 i.e. 12 months

Date of expenditure

(A)

Amount of expenditure

(B)

Period outstanding from the date of expenses

( C)

Weighted average accumulated expenditure

(D) = {B*C/12}

1/1/2016

500,000

12 months

500,000

4/1/2016

600,000

9 months

450,000

7/1/2016

300,000

6 months

150,000

12/31/2016

100,000

0 months

0

Total weighted average accumulated expenditure

1,100,000

Additional Info:

Calculation of Actual Interest

Specific debt : 800,000*10%

80,000

General debt: 2,000,000*5%

100,000

Total Actual Interest

180,000

Calculation of Avoidable Interest

Weighted Average Accumulated Expenditure

Rate of Interest

Amount of Avoidable Interest

800,000

10%

80,000

300,000

5%

15,000

1,100,000

95,000

Avoidable Interest is less than actual interest.

Amount of interest to be capitalized is $95,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
On January 1, 2016, Roger Company began construction of a new warehouse. The building was finished...
On January 1, 2016, Roger Company began construction of a new warehouse. The building was finished and ready for use on December 31, 2016. Roger Spent $4,650,000 on the building. These expenditures were made evenly throughout the year. Roger's only outstanding interest-bearing debt throughout 2016 was a $5,000,000 not payable. The interest rate on this debt was 6%. What amount should be reported as an interest expense on Roger's 2016 income statement?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
Company Corp. is constructing a building. The following information pertains to the construction of the building....
Company Corp. is constructing a building. The following information pertains to the construction of the building. Use the given Excel spreadsheet to prepare journal entries and move amounts to the general ledger. Afterwards, prepare the trial balances on the last tab of the Excel file. Submit only 1 Excel file per group. This set of entries is due 10/24/2016 at midnight. 1) On 1/1/2016, company borrows $2,000,000 at 12% for 8 years to finance the new construction project. Payments are...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date                                                   Expenditures March 1, 2019                                  $   1,200,000 May 1, 2019                                          1,680,000 August 1, 2019                                      3,000,000 September 30, 2019                              4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
Azalea Company began construction on a new office building on Jan. 1 of this year. The...
Azalea Company began construction on a new office building on Jan. 1 of this year. The building was completed on Sept. 30. Expenditures were made of $200,000 on Jan. 1; $300,000 on Sept. 1; and $300,000 on Dec. 31. The weighted average accumulated expenditures are: Group of answer choices $500,000 $300,000 $350,000 $400,000
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT