Snappy Company uses job-order costing and applies overhead costs
to jobs using a pre-determined overhead rate...
Snappy Company uses job-order costing and applies overhead costs
to jobs using a pre-determined overhead rate of $12 per direct
labor hour.
During 2020, Snappy Company worked on the following jobs
Job #16 Job #28 Job #35
beginning cost ............. $3,500 $1,600 $2,000
direct materials used ...... $2,800 $3,700 $2,600
direct labor cost .......... $2,000 $5,300 $3,600
direct labor hours ......... 200 hours 300 hours 280 hours
By the end of 2020, Job #16 and Job #28 had been completed....
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate,
Ending Balance of WIP, Finished Goods, and COGS
At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate,
Ending Balance of WIP, Finished Goods, and COGS
At the beginning of March, Mendez Company had two jobs in
process, Job 86 and Job 87, with the following accumulated cost
information:
Job 86
Job 87
Direct materials
$4,800
$1,600
Direct labor
1,200
3,000
Applied overhead
888
2,220
Balance, March 1
$6,888
$6,820
During March, two more jobs (88 and 89) were started. The
following direct materials and direct labor costs were added to...
Lott Company uses a job order cost system and applies overhead
to production on the basis...
Lott Company uses a job order cost system and applies overhead
to production on the basis of direct labor costs. On January 1,
2020, Job 50 was the only job in process. The costs incurred prior
to January 1 on this job were as follows: direct materials $20,000,
direct labor $12,000, and manufacturing overhead $16,000. As of
January 1, Job 49 had been completed at a cost of $90,000 and was
part of finished goods inventory. There was a $15,000...
Parker Company has a job-order costing system and uses a
pre-determined overhead rate based on direct...
Parker Company has a job-order costing system and uses a
pre-determined overhead rate based on direct labor hours to apply
manufacturing overhead to jobs. At the beginning of the year,
manufacturing overhead and direct labor hours for the year were
estimated at $50,000 and 25,000 hours respectively. In June, Job
#461 was started, completed, and sold to a customer. Materials cost
on the job totaled $4,000, and labor costs were $5 per hour and
totaled $1,500. Sales commissions incurred on...
Br3-Pf Company uses a job-order costing system and applies
overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies
overhead costs to jobs using a plant-wide rate of 90% of
direct materials cost. Br3-Pf Company began work on four
jobs during June. Information related to the four jobs
appears below:
Job #1 Job #2
COSTS ADDED DURING JUNE
direct materials .............. $5,800 $7,500
direct labor .................. $7,300 $6,300
Job #3 Job #4
COSTS ADDED DURING JUNE
direct materials .............. $8,200 $6,400
direct labor .................. $7,920 $7,560
By the end of...
Langdon Company manufactures custom
designed toy sailboats. The company uses a job order costing
system. Overhead...
Langdon Company manufactures custom
designed toy sailboats. The company uses a job order costing
system. Overhead is applied based on direct labor hours. Estimated
overhead for 2018 is $11,840 and the company estimates it will use
7,400 direct labor hours. The following events occurred in
March.
The company purchased materials for $800 on account.
The production supervisor requisitioned 15 sheets of fiberglass
for constructing the boats. The fiberglass was in stock and
originally cost $3 a sheet.
Direct labor on...
Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses
activity-based costing...
Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses
activity-based costing to apply overhead to jobs. Heitger
identified three overhead activities and related drivers. Budgeted
information for the year is as follows:
Activity
Cost
Driver
Amount of
Driver
Materials handling
$ 72,000
Number of moves
3,000
Engineering
165,000
Number of change orders
10,000
Other overhead
280,000
Direct labor hours
50,000
Heitger worked on four jobs in July. Data are as follows:
Job 13-43
Job 13-44...
The Eagles Corporation uses a normal job-order costing system in
its only production department. Overhead is...
The Eagles Corporation uses a normal job-order costing system in
its only production department. Overhead is applied to jobs by a
plant-wide overhead rate based on direct labor hours. The first
year of operation began on December 1, 2016. During the month of
December, Eagles Corporation purchased direct material with a total
cost of $4,000. Of the $4,000, Eagles Corporation used $500 on Job
100. Job 100 was the only job worked during the month of December.
Eagles Corporation also...
2. Job Order Costing – Application of Overhead using a
pre-determined OH rate (4pts): Skaro, Ltd....
2. Job Order Costing – Application of Overhead using a
pre-determined OH rate (4pts): Skaro, Ltd. is
a manufacturer that uses a job-order costing system. Assume Skaro
uses a single plantwide predetermined Factory OH rate to apply
overhead, and bases their predetermined OH rate on machine hours
(Mh). At the beginning of 2020, the firm made the following
estimates for the upcoming year:
Estimated Direct labor hours (DLh)
5,100 DLh
Estimated Machine hours (Mh)
22,000 Mh
Estimated total Variable Factory...