Question

Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS

At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information:

Job 86 Job 87
Direct materials $4,800 $1,600
Direct labor 1,200 3,000
Applied overhead 888 2,220
Balance, March 1 $6,888 $6,820

During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to the four jobs during the month of March:

Job 86 Job 87 Job 88 Job 89
Direct materials $3,000 $7,000 $2,100 $1,500
Direct labor 800 6,000 900 500

At the end of March, Jobs 86, 87, and 89 were completed. Only Job 87 was sold. On March 1, the balance in Finished Goods was zero.

Required:

1. Calculate the overhead rate based on direct labor cost.

$ %

2. Prepare a brief job-order cost sheet for the four jobs. Show the balance as of March 1 as well as direct materials and direct labor added in March. Apply overhead to the four jobs for the month of March, and show the ending balances.

Mendez Company
Job-Order Cost Sheets
For the Month of March
Job 86 Job 87 Job 88 Job 89
Beginning balance, March 1 $ $ $ $
Direct materials
Direct labor
Applied overhead
Total, March 31 $ $ $ $

3. Calculate the ending balances of Work in Process and Finished Goods as of March 31.

Work in Process: $
Finished Goods: $

4. Calculate the Cost of Goods Sold for March.

$

Homework Answers

Answer #1

1. Calculate the overhead rate based on direct labor cost.

Overhead rate = Overhead applied*100/direct labour cost

                     = 888*100/1200

Overhead rate = 74% of direct labour cost

2. Prepare a brief job-order cost sheet for the four jobs.

Job 86 Job 87 Job 88 Job 89
Beginning balance, March 1 6888 6820
Direct materials 3000 7000 2100 1500
Direct labour 800 6000 900 500
Applied overhead 592 4440 666 370
Total March 31 11280 24260 3666 2370

3. Calculate the ending balances of Work in Process and Finished Goods as of March 31.

Work in process = Job 88 = 3666

Finished goods = 11280+2370 = 13650

4. Calculate the Cost of Goods Sold for March.

Cost of goods sold = $24,260

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.The balance in the Work in Process account equals: the balance in the Finished Goods inventory...
1.The balance in the Work in Process account equals: the balance in the Finished Goods inventory account. the balances on the job cost sheets of uncompleted jobs. the balance in the Manufacturing Overhead account. the balance in the Cost of Goods Sold account. 2. The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,039. A total of 32 direct labor-hours and 175 machine-hours were worked on the job. The...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $ 5,000 $ 7,000 $ 1,500 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the...
Yurman Inc. uses a job-order costing system. During the month of May, the following transactions occurred:...
Yurman Inc. uses a job-order costing system. During the month of May, the following transactions occurred: May 1 Purchased materials on account for $29,680. 3 Requisitioned materials totaling $24,480 for use in production. Of the total, $9,220 was for Job 58, $8,940 for Job 59, and the remainder for Job 60. 31 Incurred direct labor for the month of $28,800, with an average wage of $16 per hour. Job 58 used 790 hours; Job 59, 590 hours; and Job 60,...
Problem #1 (Job Order Costing) Jen's has the following transactions for the month of November: 1....
Problem #1 (Job Order Costing) Jen's has the following transactions for the month of November: 1. Purchased materials on account for $111,482. 2. Materials Requisitioned for $82,383. 3. Direct Labor for the month was incurred (but not yet paid) of $51,000 4. Actual Overhead for the month was $33,000. It has not been paid yet (Charge to Various Payables) 5. Overhead is applied to production at the rate of 70% of direct labor. 6. Jobs totaling $56,000 were transferred from...
Determine cost of jobs and ending balance in work in process and overhead accounts. (LO 2,...
Determine cost of jobs and ending balance in work in process and overhead accounts. (LO 2, 3, 4), AP Don Lieberman and Associates, a CPA firm, uses job order costing to capture the costs of its audit jobs. There were no audit jobs in process at the beginning of November. Listed below are data concerning the three audit jobs conducted during November. Lynn Brian Mike Direct materials $600 $400 $200 Auditor labor costs $5,400 $6,600 $3,375 Auditor hours 72 88...
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 54% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $6,400 $8,400 $2,900 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March,...
Atlantic Manufacturing Corp operates a job-order costing system and applies overhead cost to jobs on the...
Atlantic Manufacturing Corp operates a job-order costing system and applies overhead cost to jobs on the basis of direct labor cost. The company has provided the following data: (Amounts in dollars $) Estimated direct labor cost              85,000 Actual direct labor cost              87,000 Estimated manufacturing overhead costs           148,750 Actual manufacturing overhead costs           147,300 Purchases of raw materials (all direct)           141,000 Beginning Ending Raw materials              23,000                   16,000 Work in Process              44,000                   36,000 Finished...
What is the ending balance for Raw Materials? __________________________ What is the Cost of Goods Manufactured?...
What is the ending balance for Raw Materials? __________________________ What is the Cost of Goods Manufactured? _______________________________ What is the Cost of Goods Sold on the income statement____________________ How much overhead was actually incurred this period? __________________________ What is the net income for the period? _________________________________ Riverwards Inc. is a small company that manufactures irrigation systems. The line workers earn $32/hour. The company uses job order costing and applies manufacturing overhead on the basis of labor hours. At the beginning...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT