The following data are average times per order over the last month for Groot Corp.
hours |
|
Move time |
1 |
Inspection time |
91 |
Queue time |
3 |
Wait time to start production |
2 |
Process time |
5 |
Q.) What is Manufacturing Cycle Efficiency (MCE)? Use two decimal places in the answer (for example, if the answer is 83%, key in "0.83").
Move time = 1 hour
Inspection time = 91 hours
Queue time = 3 hour
Wait time to start production = 2 hours
Process time = 5 hours
Manufacturing cycle time = Process time + Inspection time + Move time + Queue time
= 5 + 91 + 1 + 3
= 100 hours
Manufacturing cycle efficiency = = Process time/ Manufacturing
cycle time
= 5/100
= 0.05
kindly give a positive rating if you are satisfied with the solution. Please ask if you have any query related to the question, Thanks.