DataSpan, Inc., automated its plant at the start of the current
year and installed a flexible manufacturing system. The company is
also evaluating its suppliers and moving toward Lean Production.
Many adjustment problems have been encountered, including problems
relating to performance measurement. After much study, the company
has decided to use the performance measures below, and it has
gathered data relating to these measures for the first four months
of operations.
Month |
|||||
1 |
2 |
3 |
4 |
||
Throughput time (days) |
? |
? |
? |
? |
|
Delivery cycle time (days) |
? |
? |
? |
? |
|
Manufacturing cycle efficiency (MCE) |
? |
? |
? |
? |
|
Percentage of on-time deliveries |
79% |
80% |
85% |
92% |
|
Total sales (units) |
10,550 |
10,450 |
10,430 |
10,560 |
|
Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:
Average per Month (in days) |
|||||||||
1 |
2 |
3 |
4 |
||||||
Move time per unit |
0.5 |
0.3 |
0.6 |
0.7 |
|||||
Process time per unit |
0.6 |
0.5 |
0.4 |
0.6 |
|||||
Wait time per order before start of production |
9.0 |
8.0 |
5.0 |
4.0 |
|||||
Queue time per unit |
3.2 |
3.8 |
2.4 |
1.3 |
|||||
Inspection time per unit |
0.8 |
0.3 |
0.4 |
0.5 |
|||||
3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)
|
3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)
|
3a.
Details for Month 5 are as follows
Particular | Days |
Move time | 0.7 |
Process time | 0.6 |
Inspection time | 0.5 |
Queue time | 0 |
Through put= Move time+ Process time+ Inspection time+Queue time
=(0.7+0.6+0.5+0)days=1.8 days
MCE= Process time/ Throughput time
=0.6/1.8=33.33%
3b.
Details for Month 6 are as follows
Particulars | Days |
Move time | 0.7 |
Process time | 0.6 |
Inspection time | 0 |
Queue time | 0 |
Throughout time=(0.7+0.6)days=1.3days
MCE= 0.6/1.3=46.2%
Month | Throughput (in days) | MCE (%) |
Month 1 |
1.8 |
33.33 |
Month 2 | 1.3 | 46.2 |