Tahoe Company records the time (in hours) required to fill orders at her pet supply store. Data concerning a particular order is as follows:
wait time 4.4
process time 2.2
inspection time .4
move time .7
queue time 1.8
The manufacturing cycle efficiency (MCE) was closest to
.29
.23
.43
.32
The manufacturing cycle efficiency (MCE) is the ratio of production time spent of value adding activities over the manufacturing cycle time.
Here the manufacturing cycle times = Process time + Inspection time + move time + Queue time
So Manufacturing cycle time = 2.2+ .4+ .7+ 1.8 = 5.1 hours,
now process time is the actual time for which the process is being made it is the value added time which adds real value to the product.
Value added time = 2.2 hours.
So Manufacturing efficiency time = (value added time or process time) / manufacturing cycle time
manufacturing efficiency time = 2.2 / 5.1 = .4313
Thus Correct option is ----- C i.e .43