Question

13. Austen Corporation keeps careful track of time required to fill orders. The times recorded for...

13. Austen Corporation keeps careful track of time required to fill orders. The times recorded for a particular order appear below:

Hours Move time 2.6

Wait time 13.3

Queue time 8.5

Process time 1.5

Inspection time 0.2

Question: The manufacturing cycle efficiency (MCE) was closest to: A. 0.20 B. 0.06 C. 0.12 D. 0.96 E. None of the above

Homework Answers

Answer #2

OPTION - C. 0.12.

Throughput time = Process time+Inspection time + Move time + Queue time

If you have any doubts please comment on the answer.

answered by: anonymous
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Pinkton Corporation keeps careful track of the time required to fill orders. The times recorded...
1. Pinkton Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 5.1 Wait time 30.3 Queue time 4.4 Process time 0.6 Inspection time 0.4 The delivery cycle time was: (Round your intermediate calculations to 1 decimal place.) Multiple Choice 5.1 hours 9.5 hours 39.8 hours 40.8 hours 2. Navern Corporation manufactures and sells custom home elevators. From the time an order is placed until the time...
Tahoe Company records the time (in hours) required to fill orders at her pet supply store....
Tahoe Company records the time (in hours) required to fill orders at her pet supply store. Data concerning a particular order is as follows: wait time 4.4 process time 2.2 inspection time .4 move time .7 queue time 1.8 The manufacturing cycle efficiency (MCE) was closest to .29 .23 .43 .32
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.3 Inspection time 0.2 Process time 1.4 Move time 1.3 Queue time 2.5 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most...
Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 13.2 Inspection time 0.7 Process time 1.60 Move time 0.6 Queue time 2.2 Required: a. Compute the throughput time.(Enter your answer rounded to 1 decimal...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most...
Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Days Wait time 15.9 Inspection time 0.6 Process time 3.8 Move time 0.3 Queue time 3.2 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the production...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:   Inspection time 0.6 days   Wait time (from order to start of production) 16.8 days   Process time 3.5 days   Move time 0.6 days   Queue time 3.9 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.3 days Wait time (from order to start of production) 16.0 days Process time 2.5 days Move time 1.5 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.2 days Wait time (from order to start of production) 15.4 days Process time 3.3 days Move time 1.3 days Queue time 4.1 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.8 days Wait time (from order to start of production) 15.3 days Process time 3.3 days Move time 1.5 days Queue time 4.4 days Required: 1. Compute the throughput time. (Round your answer to...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...