13. Austen Corporation keeps careful track of time required to fill orders. The times recorded for a particular order appear below:
Hours Move time 2.6
Wait time 13.3
Queue time 8.5
Process time 1.5
Inspection time 0.2
Question: The manufacturing cycle efficiency (MCE) was closest to: A. 0.20 B. 0.06 C. 0.12 D. 0.96 E. None of the above
OPTION - C. 0.12.
Throughput time = Process time+Inspection time + Move time + Queue time
If you have any doubts please comment on the answer.