Question

Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...

Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data.

Raw Materials Inventory        $4,100             Manufacturing Overhead Applied      $31,200

Work in Process Inventory      $5,250             Manufacturing Overhead Incurred     $28,800

Subsidiary data for Work in Process Inventory on June 1 are as follows.

Job Cost Sheets

  Customer Job                         

Cost Element Rodgers           Stevens           Linton             

Direct materials                                                          $600                $700                $800

Direct labor                                                                 300. 600 500

Manufacturing overhead                                            375 750   625

                                                                                    $1,275 $2,050 $1,925

            During June, raw materials purchased on account were $5,000, and all wages were paid. Additional overhead costs consisted of depreciation on equipment $800 and miscellaneous costs of $400 incurred on account.

            A summary of materials requisition slips and time tickets for June shows the following.

Customer Job                         Materials Requisition Slips                Time Tickets

Rodgers                                               $700                                        $1,000

Koss                                                     2,100   900

Stevens 400 400

Linton                                                  1,400                                       1,100                          

Rodgers 400                                          300

5,000                                       3,700

General use                                        1,400                                       1,000

                                                            $6,400                                     $4,700

            Overhead was charged to jobs at the same rate of $1.25 per dollar of direct labor cost. The patios for customers Rodgers, Stevens, and Linton were completed during June and sold for a total of $18,600. Each customer paid in full.

Instructions

Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing overhead cost incurred; (2) assignment of direct materials, labor, and overhead to production; and (3) completion of jobs and sale of goods.
Post the entries to Work in Process Inventory.
Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs.
Prepare a cost of goods manufactured schedule for June.

Homework Answers

Answer #1

A . Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing overhead cost incurred.(2) assignment of direct materials, labor, and overhead to production; and (3) completion of jobs and sale of goods.

1

Particulars

Debit

Credit

Raw materials inventory

5000

   Account payable

5000

Factory labor

4700

   Cash

4700

Manufacturing overhead

1200

    Accumulated depreciation equipment

800

    Account payable

400

2

Work in process inventory

5000

Manufacturing overhead

1400

   Raw materials inventory

6400

Work in process inventory

3700

Manufacturing overhead

1000

   Factory labor

4700

Work in process inventory (3700*1.25)

4625

   Manufacturing overhead

4625

3

Finished goods inventory

14450

   Work in process inventory

14450

Job

Direct materials

Direct labor

Manufacturing overhead

Total costs

Rodgers

1700

1600

2000

5300

Stevens

1100

1000

1250

3350

Linton

2200

1600

2000

5800

Manufacturing overhead * direct labor *1.25

14450

Cash

18600

  Sales

18600

Cost of goods sold

14450

   Finished goods inventory

14450

.

B . Post the entries to Work in Process Inventory

01-06-17

Balance

5250

30-06-17

14450

Direct materials

5000

Direct labor

3700

Overhead applied

4625

30-06-17

Balance

4125

.

C. Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs

Work in process

4125

Job : koss

   Direct materials

2100

   Direct labor

900

   Manufacturing overhead

1125

4125

.

D Prepare a cost of goods manufactured schedule for June

CASE INC.

cost of goods manufactured schedule

For the month ended June 30 , 2017

Work in process June 1

5250

Direct materials used

5000

Direct labor

3700

Manufacturing overhead applied

4625

   Total manufacturing costs

13325

Total cost of work in process

18575

Less work in process June 30

4125

cost of goods manufactured

$14450

.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance...
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,940 and two jobs in process: Job No. 429 $2,160, and Job No. 430 $1,780. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,770 $2,100 430 3,910 3,300 431 4,920 $11,600 8,200 $13,600 General use 940 1,460 $12,540 $15,060 Ivanhoe Company applies manufacturing overhead to jobs at...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs:         Work in Process Balance on 3/1 Job 33 $ 6,000 Job 34 3,900 $ 9,900 Source documents revealed the following during March:          Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 2,200 $ 5,700 Completed and sold Job 34 2,400 3,000...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job...
Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: $600 At the beginning of January the company had the following work-in-process inventories: Job 21 $13,000 Job 25 $9,000 During January, the following activities took place: 1. Started jobs 26 and 27. 2. Purchased raw materials in January: $12,000 Requisitioned...
Fort Corporation had the following transactions during its first month of operations: 1. Purchased raw materials...
Fort Corporation had the following transactions during its first month of operations: 1. Purchased raw materials on account, $85,000. 2. Raw Materials of $30,000 were requisitioned to the factory. An analysis of the materials requisition slips indicated that $6,000 was classified as indirect materials. 3. Factory labor costs incurred were $175,000. 4. Time tickets indicated that $145,000 was direct labor and $30,000 was indirect labor. 5. Overhead costs incurred were $198,000. 6. Manufacturing overhead was applied at the rate of...
The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...
The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,500 $ 3,800 $ 2,800 Direct labor 800 1,460 1,900 Overhead 480 876 1,140 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $800; direct labor,...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,000 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 480 22 300 360 24 1,640 27 1,560 31 700 840 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost (a) Answer the following questions. (1)...
Serial Problem Business Solutions LO P1, P2, P3 The computer workstation furniture manufacturing that Santana Rey...
Serial Problem Business Solutions LO P1, P2, P3 The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,500 $ 3,500 $ 2,800 Direct labor 900 1,600 1,900 Overhead 450 800 950 How much total direct labor cost is incurred in June? Job 602 Job 603...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
Christopher’s Custom Cabinet Company uses a job order cost system with overhead applied as a percentage...
Christopher’s Custom Cabinet Company uses a job order cost system with overhead applied as a percentage of direct labor costs. Inventory balances at the beginning of 2018 follow: Raw Materials Inventory $ 16,100 Work in Process Inventory 6,600 Finished Goods Inventory 21,700 The following transactions occurred during January: (a) Purchased materials on account for $27,200. (b) Issued materials to production totaling $20,900, 90 percent of which was traced to specific jobs and the remainder of which was treated as indirect...
Which of the following statements about job-order costing is not true? Materials are traced to jobs...
Which of the following statements about job-order costing is not true? Materials are traced to jobs using materials requisition forms. I ndirect labor is traced to jobs using time tickets. Manufacturing overhead cannot be traced directly to jobs, so it is assigned using an overhead allocation rate. Manufacturing overhead costs are applied to jobs by crediting the Manufacturing Overhead account and debiting it to Work in Process Inventory.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT