Question

A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...

A job cost sheet of Sandoval Company is given below.

Job Cost Sheet

JOB NO. 469 Quantity 2,000
ITEM White Lion Cages Date Requested 7/2
FOR Todd Company Date Completed 7/31


Date

Direct
Materials

Direct
Labor

Manufacturing
Overhead

7/10 700
12 900
15 400 480
22 300 360
24 1,640
27 1,560
31 700 840
Cost of completed job:      
   Direct materials      
   Direct labor       
   Manufacturing overhead       
Total cost       
Unit cost

(a)

Answer the following questions.

(1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job?

Source Documents
Direct materials                                                                       Materials requisition slipsPredetermined overhead rateTime tickets
Direct labor                                                                       Materials requisition slipsPredetermined overhead rateTime tickets
Manufacturing overhead                                                                       Materials requisition slipsPredetermined overhead rateTime tickets


(2) Overhead is applied on the basis of direct labor cost. What is the predetermined manufacturing overhead rate?

Predetermined manufacturing overhead rate %


(3) What are the total cost and the unit cost of the completed job? (Round unit cost to 2 decimal places, e.g. 1.25.)

Total cost of the completed job $
Unit cost of the completed job $

Save for Later

Attempts: 0 of 1 used

Submit Answer

(b)

Prepare the entry to record the completion of the job. (Credit account titles are automatically indented when amount is entered. Do not indent manually.)

Date

Account Titles and Explanation

Debit

Credit

July 31

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:        Direct materials        Direct labor         Manufacturing overhead      Total cost      Unit cost (1) What are the source documents for direct materials, direct labor, and...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost A job cost sheet of Sandoval...
Job Cost Sheet JOB NO. 469 Quantity 2,000 ITEM White Lion Cages Date Requested 7/2 FOR...
Job Cost Sheet JOB NO. 469 Quantity 2,000 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 500 600 22 300 360 24 1,620 27 1,540 31 700 840 (2) Overhead is applied on the basis of direct labor cost. What is the predetermined manufacturing overhead rate? (3) What are the total cost and the unit cost of the completed job? (Round unit cost...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 7,000 7,000 4,900 8 7,000 12 7,000 5,600 25 2,300 27 4,000 3,200 16,300 18,000 13,700 Cost of completed job:    Direct materials $ 16,300    Direct labor 18,000    Manufacturing overhead 13,700 Total cost $ 48,000 Unit cost ($ 48,000 ÷ 2,000) $ 24.00 (a) On the basis of the foregoing data, answer the...
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance...
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,940 and two jobs in process: Job No. 429 $2,160, and Job No. 430 $1,780. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,770 $2,100 430 3,910 3,300 431 4,920 $11,600 8,200 $13,600 General use 940 1,460 $12,540 $15,060 Ivanhoe Company applies manufacturing overhead to jobs at...
Job 652 was recently completed. The following data have been recorded on its job cost sheet....
Job 652 was recently completed. The following data have been recorded on its job cost sheet. Direct materials=$59,900 Direct labor-hours=1,225 DLHs Direct labor wage rate= $14 per DLH Number of units completed=3,700 The company applies manufacturing overhead on the basis of direct labor hours. The predetermined overhead rate is $32 per direct labor hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round answer to 2 decimal places.) Unit product cost=????
Job 652 was recently completed. The following data have been recorded on its job cost sheet:...
Job 652 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 61,900 Direct labor-hours 1,229 DLHs Direct labor wage rate $ 12 per DLH Number of units completed 4,100 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $36 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
Job 243 was recently completed. The following data have been recorded on its job cost sheet:...
Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 49,370 Direct labor-hours 410 labor-hours Direct labor wage rate $ 12 per labor-hour Machine-hours 491 machine-hours Number of units completed 2,800 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to...
The following data have been recorded for recently completed Job 674 on its job cost sheet....
The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,102. A total of 41 direct labor-hours and 197 machine-hours were worked on the job. The direct labor wage rate is $23 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $25 per machine-hour. The total cost for the job on its job cost sheet would be: Multiple Choice $4,926 $10,115 $7,970...
The following data have been recorded for recently completed Job 450 on its job cost sheet....
The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $1,678. A total of 30 direct labor-hours and 46 machine-hours were worked on the job. The direct labor wage rate is $12 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. What is the total cost for Job 450? a.) 2,770 b.) 2,590 c.) 1,754 d.) 2,866
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT