Question

Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job...

Sheds, Inc. designs and builds sheds and outbuildings for individual customers.

The company uses a job cost system and treats each customer's order as a separate job.

At the beginning of January the company had the following raw material inventory:

$600

At the beginning of January the company had the following work-in-process inventories:

Job 21

$13,000

Job 25

$9,000

During January, the following activities took place:

1. Started jobs 26 and 27.

2. Purchased raw materials in January:

$12,000

Requisitioned (or used) the following raw materials to the specific jobs:

Job 21

$2,000

Job 25

$5,000

Job 26

$1,000

Job 27

$3,000

3. Incurred January manufacturing payroll:

Direct Labor

Job 21

$750

Job 25

$2,000

Job 26

$900

Job 27

$1,500

Indirect labor

$600

4. Incurred additional manufacturing overhead costs for January:

Production equipment rent

$2,000

Manufacturing supplies purchased and used

$800

Factory utilities

$500

5. Applied manufacturing overhead using a predetermined rate based on predicted annual overhead

and predicted annual direct material cost as follows:

Predicted Annual Overhead

$48,000

Predicted Annual Direct Material cost

$120,000

6. Completed jobs 25 and 27.

7. Customer for Job 27 picked up completed job and was billed the following:

Job 27

12,000

8. The company had the following period costs that they incurred:

Sales commissions

$2,000

Administrative salaries

$3,000

1. Develop the predetermined overhead rate.

2. Complete the job cost sheets provided below for the month of January:

Job 21

Job 25

Job 26

Job 27

Beginning Balance

Current costs:

Direct materials

Direct Labor

Applied overhead

Total

Homework Answers

Answer #1
1) Predetermined overhead rate
predicted annual overhead/predicted annual direct material cost
48,000/120,000
0.4
$.04 or 40%
2) Job cost sheets
job 21 job25 job26 job27
Beginning balance 13,000 9,000
Current costs:
Direct materials 2,000 5,000 1,000 3,000
Direct labor 750 2,000 900 1,500
Applied overhead 800 2000 400 1200
total 16,550 18,000 2300 5700
Applied overhead = direct material of respective job *40%
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
Dacosta Corporation had only one job in process on May 1. The job had been charged...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,500 of direct materials, $6,966 of direct labor, and $10,132 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $19.80 per direct labor-hour. During May, the following activity was recorded: Raw materials (all direct materials): Beginning balance $ 9,200 Purchased during the month $ 38,700 Used in production $ 40,000 Labor: Direct labor-hours worked during...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 40,000 Work in process $ 18,000 Finished goods $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $16.25 per direct labor-hour was based on a cost formula that estimated $650,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 50,000 Work in process $ 30,800 Finished goods $ 43,200 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $12.00 per direct labor-hour was based on a cost formula that estimated $480,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers....
Applying Overhead to Jobs, Costing Jobs Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,700 and Job 94 with a beginning balance of $7,200. Jagjit applies overhead at the rate of $6 per direct labor hour. Direct labor wages average $18 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct...
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two...
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,650, and Job 94 with a beginning balance of $7,270. Jagjit applies overhead at the rate of $9 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows: Job 93 Job 94 Job 95 Job 96 Direct materials $910 $4,590 $3,330 $1,270 Direct...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,240,200 in manufacturing overhead cost at an activity level of 573,000 machine-hours. The company spent the entire month of January working on a large order for 8,400 custom made machined parts. The company had no...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,170,000 in manufacturing overhead cost at an activity level of 556,000 machine-hours. The company spent the entire month of January working on a large order for 8,900 custom made machined parts. The company had no...
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the...
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the start of the year: job no. 101 ($84,100) and job no. 102 ($53,500). The following information is available:    a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $824,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT