Question

1.The Scandium Company is commencing a new construction project, which is to be financed by borrowing....

1.The Scandium Company is commencing a new construction project, which is to be financed by borrowing. The key dates are as follows: 15 May 20X8 Loan interest relating to the project starts to be incurred 3 June 20X8 Technical site planning commences 12 June 20X8 Expenditures on the project start to be incurred 18 July 20X8 Construction work commences According to IAS23 Borrowing costs, from what date can Scandium commence the capitalization of borrowing costs?

a. 15 May 20X8

b. 3 June 20X8

c. 12 June 20X8

d. 18 July 20X8

2.The Palila Company purchased a varnishing machine for PHP150,000 on 1 January 20X7. The company received a government grant of PHP13,500 in respect of this asset. Company policy was to depreciate the asset over 4 years on a straight-line basis and to treat the grant as deferred income. Under IAS20 Government grants and government assistance, what should be the carrying amounts of the machine and the deferred income ("DI") balance at 31 December 20X8?

a. PHP75,000 PHP6,750

b. PHP112,500 PHP10,125

c. PHP112,500 PHP10,125

d. PHP75,000 PHP13,500

3.The December 31, 2019 and 2018 comparative financial statements of World Gallery Company showed equipment with an original cost P379,000 and P344,000 with accumulated depreciation of P153,000 and P128,000, respectively. During 2019, the company purchased equipment costing P50,000, and sold equipment with a carrying value of P9,000. What amount should the company report as depreciation expense for 2019?

a. 19,000

b. 25,000

c. 31,000

d. 34,000

Homework Answers

Answer #1

ans.1 OPTION d

All relevant conditions in IAS23 para 17 are fulfilled by the date when expenditures on the project start to be incurred.

hence, the correct answer is 18 July 20X8 when Construction work commences.

ans.2 OPTION a

Carrying amount is PHP75,000, Deferred income PHP6,750 is the correct answer.

As per IAS20 para 26, where the grant is recognized as income on a systematic and rational basis over the life of the asset. The deferred income in the statement of financial position is reduced each year by the amount credited to profit or loss. The asset is depreciated over its useful life per IAS16.

ans.3 OPTION c

379,000 - 50,000 - 344,000 = 15,000 Cost of equipment sold

15,000 - 9,000 carrying amount = 6,000 Accumulated depreciation

153,000 + 6,000 - 128,000 = 31,000 Depreciation expense.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work...
On April 1, 2018, Powell hired a contractor to construct a new warehouse. The construction work commenced on June 1, 2018, and it is expected to continue through May 31, 2019. Powell made progress payments to the contractor in 2018 as follows: Date Amount June 1 $  123,000 July 1 174,000 September 1 81,000 November 1     33,000 $411,000 As stated previously, Powell took a 1-year, 8%, $175,000 construction loan to help fund the work on this project. The company also has...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,050,000 at 11% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 16% bonds $4,000,000, 11% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 840,000 March 31 1,440,000 June 30 1,088,000 September 30 840,000...
Value-Home Ltd is a construction company that recently purchased two types of equipment. Each equipment type...
Value-Home Ltd is a construction company that recently purchased two types of equipment. Each equipment type is used in a different part of a current project operation. The management has decided to use two different depreciation methods to determine depreciation charges. The data on each equipment type is summarised below: Equipment 1 Equipment 2 Purchase date 1 July 2018 1 Oct 2018 Purchase Price $93,000 $25,500 Installation Costs    2,400 2,000 Residual Value $10,000 $5,500 Useful life 8 years 4 years...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 72 October 1, 2020 40 February 1, 2021 48 April 1, 2021 30 September 1, 2021 29 October 1, 2021 15 On July 1, 2020, Crocus obtained a $88 million construction loan with a 10% interest rate. The loan was outstanding through the end of...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
1.      On December 1, 2016, Hogan Co. purchased a tract of land as a factory site...
1.      On December 1, 2016, Hogan Co. purchased a tract of land as a factory site for $780,000. The old building on the property was razed, and salvaged materials resulting from demolition were sold. Additional costs incurred and salvage proceeds realized during December 2016 were as follows: Cost to raze old building                                                        $70,000 Legal fees for purchase contract and to record ownership     $10,000 Title guarantee insurance                                                        $16,000 Proceeds from sale of salvaged materials                               $8,000             In Hogan’s December 31, 2016...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Question 36 ABC Company issues $10,000,000, 8%, 10-year bonds at 96.5 on July 1, 2019. Interest...
Question 36 ABC Company issues $10,000,000, 8%, 10-year bonds at 96.5 on July 1, 2019. Interest is paid on July 1 and January 1. The journal entry to record the issuance will include a debit to cash for $10,000,000 a credit to cash for $9,650,000 a credit to bonds payable for $9,650,000 a debit to discount on bonds payable for $350,000 Question 37 DEF Corporation retires its $100,000 face value bonds at 105 on January 1, following the payment of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT