Question

Why does the four-step process of variance analysis enhance a cost center's ability to control costs?

Why does the four-step process of variance analysis enhance a cost center's ability to control costs?

Homework Answers

Answer #1

The four steps of variance analysis to help control costs is the best approach that can be adopted by each cost center to ensure that costs are in control. These four steps help management focus on key reason of negative variance and take all the necessary steps to ensure that they are rectified and not repeated unless the variance parameters itself need revision due to change in circumstances. For example- Introduction of labor act by government increasing wages of contract worker.

These four steps are-

1. Calculation of variance- Is the variance significant? if yes then next 3 steps needs to be followed.

2. Analyze variance to identify cause of variance

3. Select performance measures to correct the problem

4. Take corrective action

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Standard cost systems can enhance operational control through the use of a.actual costs which indicate the...
Standard cost systems can enhance operational control through the use of a.actual costs which indicate the price received for units sold. b.efficiency variances which indicate the need for corrective action. c.price variances which indicate the need for better spending control. d.standard costs which indicate the desired cost of a unit of input. e.All of these choices are correct.
In the book Advanced Managerial Accounting, Robert P. Magee discusses monitoring cost variances. A cost variance...
In the book Advanced Managerial Accounting, Robert P. Magee discusses monitoring cost variances. A cost variance is the difference between a budgeted cost and an actual cost. Magee describes the following situation: Michael Bitner has responsibility for control of two manufacturing processes. Every week he receives a cost variance report for each of the two processes, broken down by labor costs, materials costs, and so on. One of the two processes, which we'll call process A , involves a stable,...
What actions are performed in the business analysis step of the new product development process? How...
What actions are performed in the business analysis step of the new product development process? How does a business carry out this step?
In the book Advanced Managerial Accounting, Robert P. Magee discusses monitoring cost variances. A cost variance...
In the book Advanced Managerial Accounting, Robert P. Magee discusses monitoring cost variances. A cost variance is the difference between a budgeted cost and an actual cost. Magee describes the following situation: Michael Bitner has responsibility for control of two manufacturing processes. Every week he receives a cost variance report for each of the two processes, broken down by labor costs, materials costs, and so on. One of the two processes, which we'll call process A , involves a stable,...
Process capability analysis is often defined as: The ability to make the process reliable and maintainable...
Process capability analysis is often defined as: The ability to make the process reliable and maintainable The inherent variability of items produced by the process The variability allowed by the specification limits The determination that the process can meet the product specifications as intended 2 points    QUESTION 97 What is the appropriate hypothesis test when you have statements such as "greater than," "exceeds," and "less than"? A two-sided test is appropriate since the direction of the difference does not...
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at...
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at $36,000 per month at a normal operating level of 10,000 units of production output. During October, actual fixed costs were $40,000, and actual production output was 12,000 units. Required a Determine the fixed overhead budget variance. b Assume that the company applied fixed overhead to production on a per-unit basis. Determine the fixed overhead volume variance. Was the fixed overhead budget variance from requirement...
29.30 Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,300 Training of machine...
29.30 Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,300 Training of machine operators 28,100 Processing returned products 17,900 Scrap processing (disposal) 26,200 Rework 8,700 Preventative maintenance 27,900 Product design 40,100 Warranty work 7,900 Finished goods inspection 22,700 From the above schedule of activity costs, determine the prevention costs. a.$96,100 b.$56,000 c.$114,000 d.$104,800 -------------- Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,400 Training of machine operators 25,400 Processing returned products 18,400 Scrap processing...
1.A total variance is calculated as Actual cost of actual input-Standard cost of actual output True...
1.A total variance is calculated as Actual cost of actual input-Standard cost of actual output True or False 2.Total variances provide useful information for determining why the differences between actual and expected production costs occurred. True or False 3. Standard costing system allows actual costs to be compared against norms for cost control purposes True or False 4. A standard is a performance benchmark or norms used for planning and control purposes. True or False 5. A total variance is...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
7. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,800 Training of machine...
7. Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $49,800 Training of machine operators 28,400 Processing returned products 16,900 Scrap processing (disposal) 25,600 Rework 5,600 Preventative maintenance 31,800 Product design 43,900 Warranty work 6,400 Finished goods inspection 22,800 From the above schedule of activity costs, determine the prevention costs. a.$60,200 b.$109,700 c.$104,100 d.$121,000
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT