29.30
Schedule of Activity Costs |
Quality Control Activities | Activity Cost |
Process audits | $49,300 |
Training of machine operators | 28,100 |
Processing returned products | 17,900 |
Scrap processing (disposal) | 26,200 |
Rework | 8,700 |
Preventative maintenance | 27,900 |
Product design | 40,100 |
Warranty work | 7,900 |
Finished goods inspection | 22,700 |
From the above schedule of activity costs, determine the prevention costs.
a.$96,100
b.$56,000
c.$114,000
d.$104,800
--------------
Schedule of Activity Costs |
Quality Control Activities | Activity Cost |
Process audits | $49,400 |
Training of machine operators | 25,400 |
Processing returned products | 18,400 |
Scrap processing (disposal) | 24,100 |
Rework | 7,900 |
Preventative maintenance | 29,500 |
Product design | 42,200 |
Warranty work | 7,600 |
Finished goods inspection | 22,900 |
From the above schedule of activity costs, determine the value-added costs.
a.$169,400
b.$227,400
c.$146,500
d.$177,000
1
Option A)
Value-added costs. =$96100
Working notes for the above answer is as under
Training Of Machine Operators |
28100 |
Preventive Maintenances |
27900 |
Product Design |
40100 |
the prevention costs |
96100 |
____________________________________________________________________
2
Option A)
the prevention costs =$169,400
Working notes for the above answer is as under
Activity Cost |
|
Process audits |
49400 |
Training of machine operators |
25400 |
Preventative maintenance |
29500 |
Product design |
42200 |
Finished goods inspection |
22900 |
value added costs |
169400 |