On May 15, the stamping department accepted Job 051507A to make 1,000 funnels. Materials requisitioned were 1,100 sheets at $1.20 per sheet and 1,150 grommets at $0.15 per set. The cost driver used by stamping department is the drop-forge strokes indicated by a machine mounted counter. Overhead is applied at $2.25 for each drop-forge stroke. Additionally, $375.00 of overhead is applied to each job due to setup and tear down. Direct labor is applied at $22.50 per hour for the machine operator and $11.10 for the machine loader. The job required 6.5 hours of labor. Upon completion, the job was transferred to Finish Goods Inventory.
Required:
Journalize all events as of May 15
15-May | Work in Process | 1492.5 | =(1100*1.2)+(1150*0.15) | |
Raw Materials | 1492.5 | |||
15-May | Work in Process | 2883.75 | =375+(1115*2.25) | |
Factory Overhead | 2883.75 | |||
15-May | Work in Process | 218.4 | =6.5*(22.5+11.1) | |
Wages Payable | 218.4 | |||
15-May | Finished Goods Inventory | 4594.65 | ||
Work in Process | 4594.65 | |||
Get Answers For Free
Most questions answered within 1 hours.