Question

1. Tammy is a general contractor and has submitted two bids for two projects (A and...

1. Tammy is a general contractor and has submitted two bids for two projects (A and B). The probability of getting project A is 0.55. The probability of getting project B is 0.78. The probability of getting at least one of the projects is 0.91.

a. What is the probability that she will get both projects?

b. Are the events of getting the two projects mutually exclusive? Explain, using probabilities.

c. Are the two events independent? Explain, using probabilities.

Homework Answers

Answer #1

a)

Using addition rule of probabilities

P(A OR B) = P(A) + P(B) - P(A and B)

0.91 = 0.55 + 0.78 - P( A and B)

So,,

P(A and B) = 0.55 + 0.78 - 0.91

= 0.42

b)

Two events are mutually exclusive if P( A and B) = 0

Since P(A and B) = 0.42 0, Events A and B are not mutually exclusive.

c)

Two events A and B are independent if P(A and B) = P(A ) * P(B)

Now ,

P(A ) * P(B) = 0.55 * 0.78 = 0.429

Since

P(A and B) P(A) * P(B) , Events A and B are not independent.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Simon is a general contractor and has submitted two bids for two projects (A and...
1. Simon is a general contractor and has submitted two bids for two projects (A and B). The probability of getting project A is 0.54. The probability of getting project B is 0.58. The probability of getting at least one of the projects is 0.87. a.       What is the probability that she will get both projects? b.       Are the events of getting the two projects mutually exclusive? Explain, using probabilities. c.       Are the two events independent? Explain, using probabilities.
Please solve the following questions related to Chapter 4: Introduction to Probability. 1. Simon is a...
Please solve the following questions related to Chapter 4: Introduction to Probability. 1. Simon is a general contractor and has submitted two bids for two projects (A and B). The probability of getting project A is 0.54. The probability of getting project B is 0.58. The probability of getting at least one of the projects is 0.87. a.       What is the probability that she will get both projects? b.       Are the events of getting the two projects mutually exclusive? Explain,...
The probability that a contractor will win a bid for contract A is 0.45; the probability...
The probability that a contractor will win a bid for contract A is 0.45; the probability that the contractor will win a bid for contract B is 0.25. The two bids are believed to be independent of each other. What is the probability that the contractor will win at least one of the two bids? Group of answer choices 0.70 0.20 0.1125 0.5875 0.5556 The probability that I get job A is 0.45; the probability that I get job B...
4. As a company manager for Claimstat Corporation there is a 0.40 probability that you will...
4. As a company manager for Claimstat Corporation there is a 0.40 probability that you will be promoted this year. There is a 0.72 probability that you will get a promotion, a raise, or both. The probability of getting a promotion and a raise is 0.28. (1) If you get a promotion, what is the probability that you will also get a raise? (2) Are getting a raise and being promoted independent events? Explain using probabilities. (3) Are these two...
3. As a company manager for Claimstat Corporation there is a 0.40 probability that you will...
3. As a company manager for Claimstat Corporation there is a 0.40 probability that you will be promoted this year. There is a 0.6 probability that you will get a promotion, a raise, or both. The probability of getting a promotion and a raise is 0.3. (1) If you get a raise, what is the probability that you will also get a promotion? (2) Are getting a raise and being promoted independent events? Explain using probabilities. (3) Are these two...
1) a. If A and B are two events, in general, P( A U B) =...
1) a. If A and B are two events, in general, P( A U B) = b. if A and B are two mutually exclusive events, P( A U B)= c. If A and B are two events, in general P( A ∩ B)= d. If A and B are two independent events, P(A ∩ B)= , since A and B being independent means ___________
An energy company is testing two shale formations for gas. The probabilty that site A has...
An energy company is testing two shale formations for gas. The probabilty that site A has gas is 60% the probabilty that both site A and B have gas is 15%. a-Calculate the probability that at least one site has gas. b-Caculate P(A given B) c- Are events A and B mutually exclusive, independent, both or neither? explain why and show mathematically.
An aerospace company has submitted bids on two separate federal government defense contracts. The company president...
An aerospace company has submitted bids on two separate federal government defense contracts. The company president believes that there is a 37% probability of winning the first contract. If they win the first contract, the probability of winning the second is 74%. However, if they lose the first contract, the president thinks that the probability of winning the second contract decreases to 54%. A. What is the probability that they win both contracts? Probability = 0.2738 B. What is the...
An aerospace company has submitted bids on two separate federal government defense contracts. The company president...
An aerospace company has submitted bids on two separate federal government defense contracts. The company president believes that there is a 42% probability of winning the first contract. If they win the first contract, the probability of winning the second is 74%. However, if they lose the first contract, the president thinks that the probability of winning the second contract decreases to 53%. A. What is the probability that they win both contracts? Probability = B. What is the probability...
ABC project consulting firm is considering bidding for two projects (Project A and B). Based on...
ABC project consulting firm is considering bidding for two projects (Project A and B). Based on past records, management believes that there is a 60% chance that project A bid will be successful, and a 40% chance that project B bid will be successful. As these two projects are completely different, it may be assumed that the success of one is totally independent of the success of the other. If these two projects are bid for concurrently, what is the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT