Question

ABC project consulting firm is considering bidding for two projects (Project A and B). Based on...

ABC project consulting firm is considering bidding for two projects (Project A and B). Based on past records, management believes that there is a 60% chance that project A bid will be successful, and a 40% chance that project B bid will be successful. As these two projects are completely different, it may be assumed that the success of one is totally independent of the success of the other. If these two projects are bid for concurrently, what is the probability that both projects bids will be successful?

Homework Answers

Answer #1

Probability that project A bid will be successful, P(A) = 60%

Probability that project B bid will be successful, P(B) = 40%

As these two projects are completely different,

and success of one is totally independent of the success of the other.

It means that events of success of each of the projects are mutually exclusive.

Using Bayes' theorem,  if these two projects are bid for concurrently, then

probability that both projects bids will be successful,

= 0.6 * 0.4

= 0.24 or 24 %

-------------------

ANSWER: 24 %

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You work for a consulting firm, and have submitted a bid for a large consulting contract....
You work for a consulting firm, and have submitted a bid for a large consulting contract. The firm's management thinks it has a 50-50 chance of landing the project. In a few weeks, the agency to which the bid was submitted sent in a request for additional information. The firm's past experience indicates that the agency asked for additional information for 72.1% of successful bids and 14.5% of unsuccessful bids. What is the probability that this particular bid will be...
A consulting firm submitted a bid for a large research project. The firm's management initially felt...
A consulting firm submitted a bid for a large research project. The firm's management initially felt they had a 50-50 chance of getting the project. However, the agency to which the bid was submitted subsequently requested additional information on the bid. Past experience indicates that for 79% of the successful bids and 42% of the unsuccessful bids the agency requested additional information. a. What is the prior probability of the bid being successful (that is, prior to the request for...
A consulting firm submitted a bid for a large research project. The firm's management initially felt...
A consulting firm submitted a bid for a large research project. The firm's management initially felt they had a 50-50 chance of getting the project. However, the agency to which the bid was submitted subsequently requested additional information on the bid. Past experience indicates that for 77% of the successful bids and 44% of the unsuccessful bids the agency requested additional information. a. What is the prior probability of the bid being successful (that is, prior to the request for...
A consulting firm submitted a bid for a large research project. Management felt their probability of...
A consulting firm submitted a bid for a large research project. Management felt their probability of winning was 0.75. The agency reviewing the bid requested additional information on the bid. Past experience indicates that for 65% of the winning bids and 45% of the losing bids the agency requested additional information. Compute the posterior probability that the bid will be successful given a request for additional information.
A consulting firm submitted a bid for a large research project. The firm’s management initially felt...
A consulting firm submitted a bid for a large research project. The firm’s management initially felt they had a 50-50 chance of getting the project. However, the agency to which the bid was submitted subsequently requested additional information on the bid. Past experience indicates that for 75% of the successful bid and 40% of the unsuccessfully bid the agency requested additional information. a) What is the prior probability of the bid being successfully (that is prior to the request for...
ABC Company, Inc. is considering two “independent” capital budgeting projects.  If the firm                          &n
ABC Company, Inc. is considering two “independent” capital budgeting projects.  If the firm                                                 accepts one of these independent projects, then the other independent project will be eliminated                                                 from consideration. True or false
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $570,000 and $770,000 B Normal probability distribution with a mean bid of $670,000 and a standard deviation of $47,000 If required, round your answers to three decimal places. If...
A firm is considering two mutually exclusive projects (named A and B). The cash flows in...
A firm is considering two mutually exclusive projects (named A and B). The cash flows in each of two states of the worlds are provided for each of the projects. The projects cost the same. Project A Project B Boom Recession Boom Recession Probability 0.6 0.4 0.6 0.4 Cash flow $200 $100 $220 $60 Payment to debt holders $100 $100 $100 $50 Distribution to stockholders $100 $0 $120 $10 3) The value of Project A is _____ and of Project...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $600,000 and $800,000 B Normal probability distribution with a mean bid of $700,000 and a standard deviation of $50,000 If required, round your answers to three...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT